Downtown Reimagined Construction Phase
About Downtown Reimagined
Downtown Reimagined is a once-in-a-generation infrastructure and streetscape revitalization project that will renew the heart of Downtown Grimsby while preserving the character that makes it unique.
The project combines the replacement of aging underground infrastructure with significant public realm improvements to create a safer, more accessible, and more vibrant downtown for residents, businesses, and visitors. By investing in critical infrastructure today, the Town is laying the foundation for a downtown that will support economic growth, enhance the visitor experience, and serve the community for decades to come.
To help reduce disruption and maintain access to businesses and residents, construction will be completed over two years.
- Phase 1 (2026): Focuses primarily on underground infrastructure renewal outside the immediate downtown core (e.g., Elm Street, Mountain Street, Christie Street, and Rossmore). This includes replacing old watermains with PVC piping.
- Phase 2 (2027): Moves the construction directly into the downtown core (Main Street between Christie and Elm) for the remaining underground and streetscape work.

Improvements will include enhanced sidewalks and accessibility features, upgraded lighting and landscaping, street furniture, improved pedestrian connections, and other public realm enhancements designed to create a more welcoming, pedestrian-friendly downtown that supports local businesses and community life.
Throughout construction, the Town remains committed to maintaining access to downtown businesses, providing regular project updates, and working closely with residents, business owners, and community partners to minimize disruption while delivering a stronger downtown for future generations.

PROJECT UPDATES
Downtown Reimagined Project Update – November 17, 2026
Crews have now completed three connections between the new watermain and existing system at Rossmore Avenue, Robinson Street and Kingsway Boulevard. Work is also underway on individual water service connections along Elm Street, with an additional crew on site to help move things along.
π§ Watermain Connections: What's Next?
Crews will continue making connections across downtown, including upcoming work at Balsam Lane, Oak Street and the GBF. Some connections will require temporary water shutdowns, with affected properties receiving at least 48 hours' notice.
π§ Mountain Road: Updated Reopening Plan
The project team has adjusted the Mountain Road reopening plan to complete the remaining watermain and service connections between Elm Street and Main Street before reopening the road. This will help avoid additional daytime closures in the area.
Weather and water testing permitting, Mountain Road is now targeted to reopen by Friday, November 27.
Read more on the News Feed below.
About Downtown Reimagined
Downtown Reimagined is a once-in-a-generation infrastructure and streetscape revitalization project that will renew the heart of Downtown Grimsby while preserving the character that makes it unique.
The project combines the replacement of aging underground infrastructure with significant public realm improvements to create a safer, more accessible, and more vibrant downtown for residents, businesses, and visitors. By investing in critical infrastructure today, the Town is laying the foundation for a downtown that will support economic growth, enhance the visitor experience, and serve the community for decades to come.
To help reduce disruption and maintain access to businesses and residents, construction will be completed over two years.
- Phase 1 (2026): Focuses primarily on underground infrastructure renewal outside the immediate downtown core (e.g., Elm Street, Mountain Street, Christie Street, and Rossmore). This includes replacing old watermains with PVC piping.
- Phase 2 (2027): Moves the construction directly into the downtown core (Main Street between Christie and Elm) for the remaining underground and streetscape work.

Improvements will include enhanced sidewalks and accessibility features, upgraded lighting and landscaping, street furniture, improved pedestrian connections, and other public realm enhancements designed to create a more welcoming, pedestrian-friendly downtown that supports local businesses and community life.
Throughout construction, the Town remains committed to maintaining access to downtown businesses, providing regular project updates, and working closely with residents, business owners, and community partners to minimize disruption while delivering a stronger downtown for future generations.

PROJECT UPDATES
Downtown Reimagined Project Update – November 17, 2026
Crews have now completed three connections between the new watermain and existing system at Rossmore Avenue, Robinson Street and Kingsway Boulevard. Work is also underway on individual water service connections along Elm Street, with an additional crew on site to help move things along.
π§ Watermain Connections: What's Next?
Crews will continue making connections across downtown, including upcoming work at Balsam Lane, Oak Street and the GBF. Some connections will require temporary water shutdowns, with affected properties receiving at least 48 hours' notice.
π§ Mountain Road: Updated Reopening Plan
The project team has adjusted the Mountain Road reopening plan to complete the remaining watermain and service connections between Elm Street and Main Street before reopening the road. This will help avoid additional daytime closures in the area.
Weather and water testing permitting, Mountain Road is now targeted to reopen by Friday, November 27.
Read more on the News Feed below.
-
Downtown Reimagined Project Update β November 17, 2026
Share Downtown Reimagined Project Update β November 17, 2026 on Facebook Share Downtown Reimagined Project Update β November 17, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β November 17, 2026 on Linkedin Email Downtown Reimagined Project Update β November 17, 2026 linkWatermain work continues to move forward across Downtown Grimsby, with three new connections now complete and service connections underway on Elm Street.
There’s also an update to the Mountain Road reopening plan. Here’s a look at the latest construction progress, upcoming work and what residents and businesses can expect in the days ahead.
Watermain milestone: Three connections complete
The new watermain has now been connected to the existing system at three locations:
- Rossmore Avenue
- Robinson Street
- Kingsway Boulevard
These connections required temporary lane closures and traffic control due to the location of the watermain and the space needed for equipment. Where possible, crews are completing this work during the day, with efforts to keep roads and businesses open and accessible.
There are more watermain connections ahead, and some will require temporary water shutdowns. Here’s what you need to know:
- Some connections can be completed without interrupting water service.
- If a building is without water, affected occupants will receive at least 48 hours' notice.
- Most shutdowns are expected to last between four and eight hours, depending on the location and complexity of the work.
With the new watermain connected, crews have also started individual service connections on Elm Street, west of Mountain Road.
Elm Street: More crews working on service connections
A third crew is now on site digging service trenches ahead of the reconnection crew. This additional crew is helping move the work along more quickly.
Unlike larger watermain connections, individual service connections are generally quicker, usually taking approximately 30 to 60 minutes per building. During this time, the building's water service will be temporarily shut off while the old connection is disconnected and the new one is hooked up.
Once the underground work is complete, a separate subcontractor will return for final restoration, including sidewalks, curbs and sod. Some restoration work, particularly sod, is expected to continue into 2027.
LOOK AHEAD: WHAT TO EXPECT THIS WEEK
Here’s a look at the work planned for the next few days:

Wednesday, November 18
- Crews will install the Balsam Lane hydrant and connection, along with a large-diameter service on Main Street East.
- Servicing work on Main Street East will necessitate a single lane closure.
- Some parking near the work area on Balsam will be affected, but most of the parking lot will remain open.
Thursday, November 19
- Crews will complete watermain connections to Oak Street and the GBF.
- A temporary water shutdown will affect all of Oak Street. Notices have been hand-delivered to affected properties.
Friday, November 20
- If the scheduled work is completed on time, crews will return to Main Street East to connect services between Robinson Street and Elm Street.
- One lane will be closed while the excavator works from the roadway toward the buildings. Flag persons will direct traffic through the area.
- Sidewalks will close temporarily as equipment crosses them. The contractor and flag persons will help direct pedestrians around the work zone.
Mountain Road: Updated reopening plan
Last week, we anticipated that the road would reopen by mid-week. However, water testing progressed faster than expected, allowing the project team to adjust the sequence of work.
If water samples pass, crews plan to complete the watermain connection at Mountain Road, along with the service connections between Elm Street and Main Street, next week.
Rather than reopen Mountain Road now and close it again to complete this work, the plan is to finish this section before reopening the road. This will avoid the need for further daytime closures in this area for that work.
The current target is to reopen Mountain Road by the end of the day on Friday, November 27.
Please note that some overnight full road closures will still be required for watermain connections at Christie Street and Main Street, as well as at Elm Street and Mountain Road.
We recognize that construction can bring temporary disruptions to daily routines and appreciate your patience and understanding as crews complete this important infrastructure work.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
Questions?
Email DTreimagined@grimsby.ca
Watermain work continues to move forward across Downtown Grimsby, with three new connections now complete and service connections underway on Elm Street.
There’s also an update to the Mountain Road reopening plan. Here’s a look at the latest construction progress, upcoming work and what residents and businesses can expect in the days ahead.
Watermain milestone: Three connections complete
The new watermain has now been connected to the existing system at three locations:
- Rossmore Avenue
- Robinson Street
- Kingsway Boulevard
These connections required temporary lane closures and traffic control due to the location of the watermain and the space needed for equipment. Where possible, crews are completing this work during the day, with efforts to keep roads and businesses open and accessible.
There are more watermain connections ahead, and some will require temporary water shutdowns. Here’s what you need to know:
- Some connections can be completed without interrupting water service.
- If a building is without water, affected occupants will receive at least 48 hours' notice.
- Most shutdowns are expected to last between four and eight hours, depending on the location and complexity of the work.
With the new watermain connected, crews have also started individual service connections on Elm Street, west of Mountain Road.
Elm Street: More crews working on service connections
A third crew is now on site digging service trenches ahead of the reconnection crew. This additional crew is helping move the work along more quickly.
Unlike larger watermain connections, individual service connections are generally quicker, usually taking approximately 30 to 60 minutes per building. During this time, the building's water service will be temporarily shut off while the old connection is disconnected and the new one is hooked up.
Once the underground work is complete, a separate subcontractor will return for final restoration, including sidewalks, curbs and sod. Some restoration work, particularly sod, is expected to continue into 2027.
LOOK AHEAD: WHAT TO EXPECT THIS WEEK
Here’s a look at the work planned for the next few days:

Wednesday, November 18
- Crews will install the Balsam Lane hydrant and connection, along with a large-diameter service on Main Street East.
- Servicing work on Main Street East will necessitate a single lane closure.
- Some parking near the work area on Balsam will be affected, but most of the parking lot will remain open.
Thursday, November 19
- Crews will complete watermain connections to Oak Street and the GBF.
- A temporary water shutdown will affect all of Oak Street. Notices have been hand-delivered to affected properties.
Friday, November 20
- If the scheduled work is completed on time, crews will return to Main Street East to connect services between Robinson Street and Elm Street.
- One lane will be closed while the excavator works from the roadway toward the buildings. Flag persons will direct traffic through the area.
- Sidewalks will close temporarily as equipment crosses them. The contractor and flag persons will help direct pedestrians around the work zone.
Mountain Road: Updated reopening plan
Last week, we anticipated that the road would reopen by mid-week. However, water testing progressed faster than expected, allowing the project team to adjust the sequence of work.
If water samples pass, crews plan to complete the watermain connection at Mountain Road, along with the service connections between Elm Street and Main Street, next week.
Rather than reopen Mountain Road now and close it again to complete this work, the plan is to finish this section before reopening the road. This will avoid the need for further daytime closures in this area for that work.
The current target is to reopen Mountain Road by the end of the day on Friday, November 27.
Please note that some overnight full road closures will still be required for watermain connections at Christie Street and Main Street, as well as at Elm Street and Mountain Road.
We recognize that construction can bring temporary disruptions to daily routines and appreciate your patience and understanding as crews complete this important infrastructure work.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
Questions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β November 13, 2026
Share Downtown Reimagined Project Update β November 13, 2026 on Facebook Share Downtown Reimagined Project Update β November 13, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β November 13, 2026 on Linkedin Email Downtown Reimagined Project Update β November 13, 2026 linkAnother week of progress for Downtown Reimagined! Crews have completed the remaining sanitary service replacements on Mountain Street as of Wednesday, November 11. Since then, work has focussed on paving cross trenches, cleaning and restoring the area, and preparing for next steps.
π§ Up Next: Overnight Paving and Road Closures
Overnight paving is scheduled for Sunday, November 15, and Monday, November 16, at the following intersections:
- Elm Street and Mountain Street
- Christie Street and Mountain Street
The intersections will be closed one at a time, between 8:00 p.m. and 7:00 a.m. the following morning.
Mountain Street, between Elm Street and Main Street, will remain closed with the existing detour in place. Weather permitting, the road is expected to reopen by mid-next week, once paving is complete.
π§ Watermain Connections: What's Next?
Final water sample results are expected late Friday, November 13. Pending satisfactory results, crews will begin connecting the new watermain to the existing system at Rossmore Avenue and Robinson Street early next week.
Once those connections are complete, crews can begin connecting individual water services along Rossmore Avenue and Main Street East.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 15
Closure Continues: Mountain Street, between Elm Street and Main Street
Until mid-next week
Mountain Street will remain closed, with the same detour in place.
Mountain Street will reopen after paving is complete, mid-week, weather permitting.
See construction and detour plans below.



Night Closures for Paving: Elm Street and Christie Street Intersections
Starting Sunday, November 15, at 8:00 p.m.
- The Elm Street and Mountain Street intersection will be closed for night paving on Sunday, November 15, followed by the Christie Street and Mountain Street intersection.
- Christie Street will start Sunday night if crews finish Elm Street, then pick up again Monday night to finish.
- The intersections will close at 8:00 p.m. and reopen at 7:00 a.m.
Watermain Connections: Rossmore Avenue and Robinson Street
To start next week, if water sample results are clean
- Final water sample results are expected late Friday, November 13.
- If the results are clean, crews will begin making connections to the existing watermain at Rossmore Avenue and Robinson Street.
- Once the watermain has been connected, crews can begin connecting individual services on Rossmore Avenue and Main Street East.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
Here's what's coming up downtown.
- β¨ Celebration of Lights: Celebrate Grimsby's holiday spirit! Nominate a beautifully decorated home or business in the Town's annual Celebration of Lights. The top three selected homes will each receive a $150 gift card. Nominations are open until December 11 at 1:00 p.m. Submit a nomination or learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Ladies’ Night: Hosted by the Downtown Grimsby BIA on Thursday, December 3, from 4:00 to 8:00 p.m.! Visit participating businesses, collect stamps on your bingo card (no purchase necessary) and enter to win prizes, including a $500 grand prize and four $50 gift cards. Learn more here.
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
While you're out for an event, make a stop at a downtown shop or restaurant and show our local businesses some love.
A LOOK BACK
Construction Recap | Week of November 2
Progress continued on Mountain Street, with crews completing the replacement of all remaining sanitary services by Wednesday, November 11. The contractor then paved the cross trenches and carried out cleaning and restoration work while awaiting sampling results.
Watermain commissioning also began Thursday night on Mountain Street, Christie Street and Main Street West.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Another week of progress for Downtown Reimagined! Crews have completed the remaining sanitary service replacements on Mountain Street as of Wednesday, November 11. Since then, work has focussed on paving cross trenches, cleaning and restoring the area, and preparing for next steps.
π§ Up Next: Overnight Paving and Road Closures
Overnight paving is scheduled for Sunday, November 15, and Monday, November 16, at the following intersections:
- Elm Street and Mountain Street
- Christie Street and Mountain Street
The intersections will be closed one at a time, between 8:00 p.m. and 7:00 a.m. the following morning.
Mountain Street, between Elm Street and Main Street, will remain closed with the existing detour in place. Weather permitting, the road is expected to reopen by mid-next week, once paving is complete.
π§ Watermain Connections: What's Next?
Final water sample results are expected late Friday, November 13. Pending satisfactory results, crews will begin connecting the new watermain to the existing system at Rossmore Avenue and Robinson Street early next week.
Once those connections are complete, crews can begin connecting individual water services along Rossmore Avenue and Main Street East.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 15
Closure Continues: Mountain Street, between Elm Street and Main Street
Until mid-next week
Mountain Street will remain closed, with the same detour in place.
Mountain Street will reopen after paving is complete, mid-week, weather permitting.
See construction and detour plans below.



Night Closures for Paving: Elm Street and Christie Street Intersections
Starting Sunday, November 15, at 8:00 p.m.
- The Elm Street and Mountain Street intersection will be closed for night paving on Sunday, November 15, followed by the Christie Street and Mountain Street intersection.
- Christie Street will start Sunday night if crews finish Elm Street, then pick up again Monday night to finish.
- The intersections will close at 8:00 p.m. and reopen at 7:00 a.m.
Watermain Connections: Rossmore Avenue and Robinson Street
To start next week, if water sample results are clean
- Final water sample results are expected late Friday, November 13.
- If the results are clean, crews will begin making connections to the existing watermain at Rossmore Avenue and Robinson Street.
- Once the watermain has been connected, crews can begin connecting individual services on Rossmore Avenue and Main Street East.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
Here's what's coming up downtown.
- β¨ Celebration of Lights: Celebrate Grimsby's holiday spirit! Nominate a beautifully decorated home or business in the Town's annual Celebration of Lights. The top three selected homes will each receive a $150 gift card. Nominations are open until December 11 at 1:00 p.m. Submit a nomination or learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Ladies’ Night: Hosted by the Downtown Grimsby BIA on Thursday, December 3, from 4:00 to 8:00 p.m.! Visit participating businesses, collect stamps on your bingo card (no purchase necessary) and enter to win prizes, including a $500 grand prize and four $50 gift cards. Learn more here.
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
While you're out for an event, make a stop at a downtown shop or restaurant and show our local businesses some love.
A LOOK BACK
Construction Recap | Week of November 2
Progress continued on Mountain Street, with crews completing the replacement of all remaining sanitary services by Wednesday, November 11. The contractor then paved the cross trenches and carried out cleaning and restoration work while awaiting sampling results.
Watermain commissioning also began Thursday night on Mountain Street, Christie Street and Main Street West.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β November 6, 2026
Share Downtown Reimagined Project Update β November 6, 2026 on Facebook Share Downtown Reimagined Project Update β November 6, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β November 6, 2026 on Linkedin Email Downtown Reimagined Project Update β November 6, 2026 linkThis week, crews worked both day and night shifts to complete the remaining watermain and service work along Main Street and Christie Street. With work on Christie Street now complete, all sections of the project's new watermain have officially been installed! This marks a significant achievement and another exciting step forward in the transformation of our downtown. The next step is to complete the remaining mainline and service connections throughout the project area. Crews will connect the newly installed pipes to the existing watermain system and individual properties, bringing us another step closer to completing this important infrastructure upgrade.
The new watermains on Elm Street, Main Street East and Rossmore Avenue also successfully passed their pressure tests this week. This important milestone clears the way for disinfection and bacteria testing to begin next week, with final connections to follow.
Crews also started repairing sanitary laterals on Mountain Street between Elm Street and Main Street.
Next week, both crews will return to day shifts, focusing on completing the remaining sanitary lateral repairs on Mountain Street. This work is expected to wrap up by the end of next week. In the meantime, Mountain Street between Elm Street and Main Street will remain closed to through traffic, with the existing detour in place.
Beginning Thursday night, crews will also start swabbing the remaining sections of new watermain on Mountain Street, Main Street and Christie Street, followed by pressure testing.
Another exciting milestone is just around the corner! Weather permitting, paving will begin Sunday night, November 15, and is expected to take about two shifts. To accommodate this work, the intersection of Main Street and Christie Street will be closed overnight from 8:00 p.m. to 7:00 a.m., beginning Sunday, November 15, until paving is complete. Mountain Street is expected to reopen once paving is complete.
Calling all young artists! There's still time to enter the Mayor's Holiday Greeting Card Contest, with submissions due Friday, November 13, at 4:30 p.m. And the holiday season is just around the corner, with the Town Tree Lighting and Fantasy of Trees both kicking off November 26.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 9
Full Closure Continues: Mountain Street, between Elm Street and Main Street
Resumes Monday, November 9
- Both crews will work day shifts to finish sanitary lateral repairs in this section.
- This work is expected to be complete by the end of the week.
- Mountain Street remains fully closed to through traffic, with the same detour in place.
- Mountain Street will reopen once paving on Main Street West and Christie Street is complete.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
- See construction plan graphic below.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night paving closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Watermain Swabbing and Pressure Testing: Mountain Street, Main Street and Christie Street
Starting Thursday, November 12
- Crews will swab (clean) the remaining new watermain on Mountain, Main, and Christie Streets.
- Pressure testing will follow.
Night Closure for Paving: Main Street and Christie Street Intersection
Starting Sunday, November 15, at 8:00 p.m.
- Weather permitting, crews will pave Main Street West and Christie Street. Paving is expected to take about two shifts.
- The intersection will be closed overnight from 8:00 p.m. to 7:00 a.m. until paving is complete.
- The intersection will reopen each morning at 7:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
Watermain Commissioning
The new watermains on Elm Street, Main Street East and Rossmore Avenue passed their pressure tests this week. Next, crews will disinfect these pipes and complete bacteria testing to confirm the water is safe. Once testing is complete, crews will make the final connections to the existing watermains and private services.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.
- π¨ Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!
A LOOK BACK
Week of November 2 Construction Recap
This week brought two major watermain milestones across the project area.
On Main Street and Christie Street, one crew worked days and the other worked nights to finish the remaining watermain and service work. Work in this area is now complete, except for the final watermain and service connections.
With Christie Street done, all of the new watermain on the project has now been installed. The remaining work is limited to mainline and service connections throughout the project area, where crews will connect the new pipe to the existing watermains and private services.
On Elm Street, Main Street East and Rossmore Avenue, the new watermains passed their pressure tests. This is a significant step that allows disinfection and bacteria testing to begin next week.
On Mountain Street, crews started sanitary lateral repairs between Elm Street and Main Street at the end of the week. This work continues next week.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
This week, crews worked both day and night shifts to complete the remaining watermain and service work along Main Street and Christie Street. With work on Christie Street now complete, all sections of the project's new watermain have officially been installed! This marks a significant achievement and another exciting step forward in the transformation of our downtown. The next step is to complete the remaining mainline and service connections throughout the project area. Crews will connect the newly installed pipes to the existing watermain system and individual properties, bringing us another step closer to completing this important infrastructure upgrade.
The new watermains on Elm Street, Main Street East and Rossmore Avenue also successfully passed their pressure tests this week. This important milestone clears the way for disinfection and bacteria testing to begin next week, with final connections to follow.
Crews also started repairing sanitary laterals on Mountain Street between Elm Street and Main Street.
Next week, both crews will return to day shifts, focusing on completing the remaining sanitary lateral repairs on Mountain Street. This work is expected to wrap up by the end of next week. In the meantime, Mountain Street between Elm Street and Main Street will remain closed to through traffic, with the existing detour in place.
Beginning Thursday night, crews will also start swabbing the remaining sections of new watermain on Mountain Street, Main Street and Christie Street, followed by pressure testing.
Another exciting milestone is just around the corner! Weather permitting, paving will begin Sunday night, November 15, and is expected to take about two shifts. To accommodate this work, the intersection of Main Street and Christie Street will be closed overnight from 8:00 p.m. to 7:00 a.m., beginning Sunday, November 15, until paving is complete. Mountain Street is expected to reopen once paving is complete.
Calling all young artists! There's still time to enter the Mayor's Holiday Greeting Card Contest, with submissions due Friday, November 13, at 4:30 p.m. And the holiday season is just around the corner, with the Town Tree Lighting and Fantasy of Trees both kicking off November 26.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 9
Full Closure Continues: Mountain Street, between Elm Street and Main Street
Resumes Monday, November 9
- Both crews will work day shifts to finish sanitary lateral repairs in this section.
- This work is expected to be complete by the end of the week.
- Mountain Street remains fully closed to through traffic, with the same detour in place.
- Mountain Street will reopen once paving on Main Street West and Christie Street is complete.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
- See construction plan graphic below.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night paving closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Watermain Swabbing and Pressure Testing: Mountain Street, Main Street and Christie Street
Starting Thursday, November 12
- Crews will swab (clean) the remaining new watermain on Mountain, Main, and Christie Streets.
- Pressure testing will follow.
Night Closure for Paving: Main Street and Christie Street Intersection
Starting Sunday, November 15, at 8:00 p.m.
- Weather permitting, crews will pave Main Street West and Christie Street. Paving is expected to take about two shifts.
- The intersection will be closed overnight from 8:00 p.m. to 7:00 a.m. until paving is complete.
- The intersection will reopen each morning at 7:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
Watermain Commissioning
The new watermains on Elm Street, Main Street East and Rossmore Avenue passed their pressure tests this week. Next, crews will disinfect these pipes and complete bacteria testing to confirm the water is safe. Once testing is complete, crews will make the final connections to the existing watermains and private services.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.
- π¨ Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!
A LOOK BACK
Week of November 2 Construction Recap
This week brought two major watermain milestones across the project area.
On Main Street and Christie Street, one crew worked days and the other worked nights to finish the remaining watermain and service work. Work in this area is now complete, except for the final watermain and service connections.
With Christie Street done, all of the new watermain on the project has now been installed. The remaining work is limited to mainline and service connections throughout the project area, where crews will connect the new pipe to the existing watermains and private services.
On Elm Street, Main Street East and Rossmore Avenue, the new watermains passed their pressure tests. This is a significant step that allows disinfection and bacteria testing to begin next week.
On Mountain Street, crews started sanitary lateral repairs between Elm Street and Main Street at the end of the week. This work continues next week.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Construction Update: Christie Parking Lot Access β November 4, 2026
Share Construction Update: Christie Parking Lot Access β November 4, 2026 on Facebook Share Construction Update: Christie Parking Lot Access β November 4, 2026 on X (formerly Twitter) Share Construction Update: Christie Parking Lot Access β November 4, 2026 on Linkedin Email Construction Update: Christie Parking Lot Access β November 4, 2026 linkWatermain construction is progressing along Christie Street towards Elizabeth Street. Crews will be working across the public parking lot entrance off Christie Street on Thursday, November 5, with impacts potentially continuing into Friday, November 6.
What to expect
π One lane of the parking lot entrance will be kept open, but access may be temporarily blocked at times as crews work across the entrance.
β³ When the entrance is blocked, drivers may need to queue and wait to enter or exit the parking lot.
π· Traffic control personnel will be on site to direct vehicles and help manage access.
β‘οΈ Drivers are encouraged to use the Ontario Street entrance to access the parking lot where possible.
See graphic below for the impacted area.

This section of watermain work is anticipated to be completed by the end of the week.
We recognize that construction can bring temporary disruptions to daily routines and appreciate your patience and understanding as crews complete this important infrastructure work.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Watermain construction is progressing along Christie Street towards Elizabeth Street. Crews will be working across the public parking lot entrance off Christie Street on Thursday, November 5, with impacts potentially continuing into Friday, November 6.
What to expect
π One lane of the parking lot entrance will be kept open, but access may be temporarily blocked at times as crews work across the entrance.
β³ When the entrance is blocked, drivers may need to queue and wait to enter or exit the parking lot.
π· Traffic control personnel will be on site to direct vehicles and help manage access.
β‘οΈ Drivers are encouraged to use the Ontario Street entrance to access the parking lot where possible.
See graphic below for the impacted area.

This section of watermain work is anticipated to be completed by the end of the week.
We recognize that construction can bring temporary disruptions to daily routines and appreciate your patience and understanding as crews complete this important infrastructure work.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β October 30, 2026
Share Downtown Reimagined Project Update β October 30, 2026 on Facebook Share Downtown Reimagined Project Update β October 30, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β October 30, 2026 on Linkedin Email Downtown Reimagined Project Update β October 30, 2026 linkThere's been plenty happening in downtown Grimsby this week, and crews are continuing to make progress!
Both construction crews worked overnight at the Main Street and Christie Street intersection from Sunday to Thursday. Along the way, they encountered some unexpected underground obstacles, including buried trolley tracks and additional Bell infrastructure. Despite these discoveries, crews advanced to Forty Mile Creek and are now heading up Christie Street.
Another important milestone: watermain commissioning is officially underway! Swabbing took place Thursday night, with commissioning activities continuing next week.
For the week ahead, crews will divide their work between day and night shifts. Starting Sunday, November 1, at 8:00 p.m., the Main Street and Christie Street intersection will be closed overnight from 8:00 p.m. to 6:00 a.m., reopening each morning at 6:00 a.m. while the night crew installs hydrants and services.
Meanwhile, the day crew will install the final stretch of watermain on Christie Street, north of Main Street, up to the dead end of Elizabeth Street past the parking lot entrance. Once that's complete, crews will move on to installing the remaining sanitary laterals on Mountain Street between Elm Street and Main Street.
Mountain Street between Elm Street and Main Street remains closed to through traffic, with the same detour in place.
And that's a wrap on GrimsBOO! More than 1,000 kids trick-or-treated through downtown, bringing plenty of Halloween spirit to our local streets and businesses. Thank you to everyone who came out to celebrate!
And the community fun continues this weekend! Join the Grimsby Glows Pumpkin Parade on Sunday, November 1, at Coronation Park, then keep the creativity going on Monday, November 2, with a special art-making station at the Grimsby Public Art Gallery for the Mayor's Holiday Greeting Card Contest. It's a great opportunity for families to get out, take part and enjoy what's happening around town!
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 2
Night Closure: Main Street and Christie Street Intersection
Starting Sunday, November 1st, at 8:00 p.m.
- The night crew will continue installing hydrants and services in the intersection.
- The intersection will be closed nightly from 8:00 p.m. to 6:00 a.m.
- The intersection will reopen every morning at 6:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
Daytime Work: Christie Street, North of Main Street
Starting Monday, November 2nd at 7:00 a.m.
- The day crew will install the final stretch of watermain north on Christie Street, up to the dead end of Elizabeth Street past the parking lot entrance.
- Please follow posted signage and traffic control.
Full Closure Continues: Mountain Street, between Elm Street and Main Street
Resumes Monday, November 2nd
- Mountain Street remains fully closed to through traffic, with the same detour in place.
- Once the Christie Street watermain is complete, crews will install the remaining sanitary laterals in this section.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks: Mountain Street Closure
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Watermain Commissioning
Watermain commissioning began this week, with swabbing carried out Thursday night. Swabbing is the first step in cleaning newly installed watermains. Crews use large, bullet-shaped sponges, called swabs, which are pushed through the pipes with water to remove debris and sediment.
This is part of a broader testing process that includes pressure testing for leaks, disinfection with chlorine and water quality testing to ensure the pipes are safe before being connected to the active water distribution system.
Commissioning activities will continue next week.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.
- π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town of Grimsby.
- π¨ Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Stop by the special art-making station outside the Gallery on Monday, November 2, to get creative! Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!
A LOOK BACK
Week of October 26 Construction Recap
It's been a productive week on site, with crews working through some unexpected discoveries along the way.
At the Main Street and Christie Street intersection, both crews worked overnight from Sunday to Thursday. They encountered buried trolley tracks and additional Bell infrastructure, but continued making progress, advancing to Forty Mile Creek and now heading up Christie Street.
Watermain commissioning also got underway, with swabbing carried out Thursday night. This marks another important step in the project!

Construction Passport Winners
The wait is over! Construction Passport winners have been announced on the Downtown Grimsby BIA social channels, and the BIA has contacted all winners.
Congratulations to everyone who won, and a big thank you to everyone who participated and supported our downtown businesses along the way!
GrimsBOO! 2026 Recap
What a turnout! GrimsBOO! 2026 brought more than 1,000 kids trick-or-treating through downtown Grimsby, filling the streets with costumes, treats and plenty of Halloween spirit.
A huge thank you to the Downtown Grimsby BIA, participating businesses, volunteers, families and everyone who came out to celebrate. It was wonderful to see the community come together and support downtown!
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
There's been plenty happening in downtown Grimsby this week, and crews are continuing to make progress!
Both construction crews worked overnight at the Main Street and Christie Street intersection from Sunday to Thursday. Along the way, they encountered some unexpected underground obstacles, including buried trolley tracks and additional Bell infrastructure. Despite these discoveries, crews advanced to Forty Mile Creek and are now heading up Christie Street.
Another important milestone: watermain commissioning is officially underway! Swabbing took place Thursday night, with commissioning activities continuing next week.
For the week ahead, crews will divide their work between day and night shifts. Starting Sunday, November 1, at 8:00 p.m., the Main Street and Christie Street intersection will be closed overnight from 8:00 p.m. to 6:00 a.m., reopening each morning at 6:00 a.m. while the night crew installs hydrants and services.
Meanwhile, the day crew will install the final stretch of watermain on Christie Street, north of Main Street, up to the dead end of Elizabeth Street past the parking lot entrance. Once that's complete, crews will move on to installing the remaining sanitary laterals on Mountain Street between Elm Street and Main Street.
Mountain Street between Elm Street and Main Street remains closed to through traffic, with the same detour in place.
And that's a wrap on GrimsBOO! More than 1,000 kids trick-or-treated through downtown, bringing plenty of Halloween spirit to our local streets and businesses. Thank you to everyone who came out to celebrate!
And the community fun continues this weekend! Join the Grimsby Glows Pumpkin Parade on Sunday, November 1, at Coronation Park, then keep the creativity going on Monday, November 2, with a special art-making station at the Grimsby Public Art Gallery for the Mayor's Holiday Greeting Card Contest. It's a great opportunity for families to get out, take part and enjoy what's happening around town!
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 2
Night Closure: Main Street and Christie Street Intersection
Starting Sunday, November 1st, at 8:00 p.m.
- The night crew will continue installing hydrants and services in the intersection.
- The intersection will be closed nightly from 8:00 p.m. to 6:00 a.m.
- The intersection will reopen every morning at 6:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
Daytime Work: Christie Street, North of Main Street
Starting Monday, November 2nd at 7:00 a.m.
- The day crew will install the final stretch of watermain north on Christie Street, up to the dead end of Elizabeth Street past the parking lot entrance.
- Please follow posted signage and traffic control.
Full Closure Continues: Mountain Street, between Elm Street and Main Street
Resumes Monday, November 2nd
- Mountain Street remains fully closed to through traffic, with the same detour in place.
- Once the Christie Street watermain is complete, crews will install the remaining sanitary laterals in this section.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks: Mountain Street Closure
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Watermain Commissioning
Watermain commissioning began this week, with swabbing carried out Thursday night. Swabbing is the first step in cleaning newly installed watermains. Crews use large, bullet-shaped sponges, called swabs, which are pushed through the pipes with water to remove debris and sediment.
This is part of a broader testing process that includes pressure testing for leaks, disinfection with chlorine and water quality testing to ensure the pipes are safe before being connected to the active water distribution system.
Commissioning activities will continue next week.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.
- π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town of Grimsby.
- π¨ Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Stop by the special art-making station outside the Gallery on Monday, November 2, to get creative! Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
- π Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- π² Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- ποΈ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!
A LOOK BACK
Week of October 26 Construction Recap
It's been a productive week on site, with crews working through some unexpected discoveries along the way.
At the Main Street and Christie Street intersection, both crews worked overnight from Sunday to Thursday. They encountered buried trolley tracks and additional Bell infrastructure, but continued making progress, advancing to Forty Mile Creek and now heading up Christie Street.
Watermain commissioning also got underway, with swabbing carried out Thursday night. This marks another important step in the project!

Construction Passport Winners
The wait is over! Construction Passport winners have been announced on the Downtown Grimsby BIA social channels, and the BIA has contacted all winners.
Congratulations to everyone who won, and a big thank you to everyone who participated and supported our downtown businesses along the way!
GrimsBOO! 2026 Recap
What a turnout! GrimsBOO! 2026 brought more than 1,000 kids trick-or-treating through downtown Grimsby, filling the streets with costumes, treats and plenty of Halloween spirit.
A huge thank you to the Downtown Grimsby BIA, participating businesses, volunteers, families and everyone who came out to celebrate. It was wonderful to see the community come together and support downtown!
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β October 23, 2026
Share Downtown Reimagined Project Update β October 23, 2026 on Facebook Share Downtown Reimagined Project Update β October 23, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β October 23, 2026 on Linkedin Email Downtown Reimagined Project Update β October 23, 2026 linkWatermain work on Mountain Street is moving along.
This week, watermain installation on Mountain Street, between Elm Street and Main Street, advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection. The servicing crew has also made good progress installing services along this stretch.
Next week, night work resumes Sunday, October 25, at 8:00 p.m., crews will prepare the previously installed watermains for commissioning, with rolling lane closures along Elm Street and Main Street that night. Starting Monday night, October 26, the Main Street and Christie Street intersection will be closed from 8:00 p.m. to 6:00 a.m., reopening each morning for the rest of the week.
Mountain Street between Elm Street and Main Street remains fully closed while work in this section continues. With both crews on nights, you'll see minimal activity on site during the day. Crews return to day shifts in this area the following week.
Meanwhile, on Main Street West, paving between Forty Mile Creek and Patton Street is tentatively scheduled for Thursday, October 29. Watermain commissioning may also begin this week.
And there's plenty to look forward to downtown! GrimsBOO! takes over downtown this Saturday, October 24, from 11:00 a.m. to 3:00 p.m.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 26
Night Work and Full Closure at Mountain Street, between Elm Street and Main Street
Starting Sunday, October 25 at 8:00 p.m.
- Crews will prepare the previously installed watermains for commissioning.
- Expect rolling lane closures along Elm Street and Main Street overnight.
- Please follow posted signage and traffic control.
Full Closure Continues: Mountain Street, between Elm Street and Main Street
- Mountain Street remains fully closed to through traffic while work in this section continues.
- Both crews will be on nights this week, so there will be minimal activity during the day.
- Crews return to day shifts in this area the following week.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and the designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Night Closure: Main Street and Christie Street Intersection
Starting Monday, October 26, for the rest of the week, from 8:00 p.m. to 6:00 a.m.
- Crews will begin work in the Main Street and Christie Street intersection.
- The intersection will be closed overnight starting 8:00 p.m.
- The intersection reopens every morning at 6:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Click here for the full construction plan

Click here for the full detour plan
Please plan ahead, allow extra travel time and follow posted signage while crews complete this next phase of the Downtown Reimagined project.
Paving: Main Street West (Forty Mile Creek to Patton Street)
Paving is tentatively scheduled for Thursday, October 29.
What to Expect: Watermain Commissioning
Before the new watermains can go into service, they need to be checked.
- Commissioning is the process of cleaning and testing the newly installed watermains before they are connected to the existing (live) watermain.
- Commissioning may begin this week. We're waiting on confirmation from the sub-contractor and will share timing once it's confirmed.

Downtown Highlights
Spooky season is here, and the holidays are right around the corner!
π» GrimsBOO! Halloween Event: Saturday, October 24, from 11:00 a.m. to 3:00 p.m. Presented by Civiconnect, this free community event brings a day of Halloween fun to downtown.
π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town, enjoy a glowing display of more than 300 carved jack-o'-lanterns, seasonal photo stations and light refreshments.
π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
Whether you're attending an event or visiting your favourite local business, we encourage you to keep exploring downtown and supporting the community that makes it special.
A LOOK BACK
Week of October 19 Construction Recap
This week, crews made strong progress on Mountain Street.
Between Elm Street and Main Street, watermain installation advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection.
The servicing crew also made good progress, installing services along the same stretch.
Each step forward brings the project closer to the next phase, while local businesses and community events continue to make downtown a place to gather and explore.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Watermain work on Mountain Street is moving along.
This week, watermain installation on Mountain Street, between Elm Street and Main Street, advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection. The servicing crew has also made good progress installing services along this stretch.
Next week, night work resumes Sunday, October 25, at 8:00 p.m., crews will prepare the previously installed watermains for commissioning, with rolling lane closures along Elm Street and Main Street that night. Starting Monday night, October 26, the Main Street and Christie Street intersection will be closed from 8:00 p.m. to 6:00 a.m., reopening each morning for the rest of the week.
Mountain Street between Elm Street and Main Street remains fully closed while work in this section continues. With both crews on nights, you'll see minimal activity on site during the day. Crews return to day shifts in this area the following week.
Meanwhile, on Main Street West, paving between Forty Mile Creek and Patton Street is tentatively scheduled for Thursday, October 29. Watermain commissioning may also begin this week.
And there's plenty to look forward to downtown! GrimsBOO! takes over downtown this Saturday, October 24, from 11:00 a.m. to 3:00 p.m.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 26
Night Work and Full Closure at Mountain Street, between Elm Street and Main Street
Starting Sunday, October 25 at 8:00 p.m.
- Crews will prepare the previously installed watermains for commissioning.
- Expect rolling lane closures along Elm Street and Main Street overnight.
- Please follow posted signage and traffic control.
Full Closure Continues: Mountain Street, between Elm Street and Main Street
- Mountain Street remains fully closed to through traffic while work in this section continues.
- Both crews will be on nights this week, so there will be minimal activity during the day.
- Crews return to day shifts in this area the following week.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and the designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Night Closure: Main Street and Christie Street Intersection
Starting Monday, October 26, for the rest of the week, from 8:00 p.m. to 6:00 a.m.
- Crews will begin work in the Main Street and Christie Street intersection.
- The intersection will be closed overnight starting 8:00 p.m.
- The intersection reopens every morning at 6:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Click here for the full construction plan

Click here for the full detour plan
Please plan ahead, allow extra travel time and follow posted signage while crews complete this next phase of the Downtown Reimagined project.
Paving: Main Street West (Forty Mile Creek to Patton Street)
Paving is tentatively scheduled for Thursday, October 29.
What to Expect: Watermain Commissioning
Before the new watermains can go into service, they need to be checked.
- Commissioning is the process of cleaning and testing the newly installed watermains before they are connected to the existing (live) watermain.
- Commissioning may begin this week. We're waiting on confirmation from the sub-contractor and will share timing once it's confirmed.

Downtown Highlights
Spooky season is here, and the holidays are right around the corner!
π» GrimsBOO! Halloween Event: Saturday, October 24, from 11:00 a.m. to 3:00 p.m. Presented by Civiconnect, this free community event brings a day of Halloween fun to downtown.
π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town, enjoy a glowing display of more than 300 carved jack-o'-lanterns, seasonal photo stations and light refreshments.
π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
Whether you're attending an event or visiting your favourite local business, we encourage you to keep exploring downtown and supporting the community that makes it special.
A LOOK BACK
Week of October 19 Construction Recap
This week, crews made strong progress on Mountain Street.
Between Elm Street and Main Street, watermain installation advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection.
The servicing crew also made good progress, installing services along the same stretch.
Each step forward brings the project closer to the next phase, while local businesses and community events continue to make downtown a place to gather and explore.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β October 16, 2026
Share Downtown Reimagined Project Update β October 16, 2026 on Facebook Share Downtown Reimagined Project Update β October 16, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β October 16, 2026 on Linkedin Email Downtown Reimagined Project Update β October 16, 2026 linkDowntown Grimsby is taking shape, one step at a time!
As work continues, crews are making progress on underground infrastructure while we keep downtown accessible for the people, businesses and experiences that make it special.
Watermain work on Main Street West is complete, apart from the final connections. Crews have also completed the remaining trench restoration on Elm Street. Overnight work at the Elm Street and Mountain Street intersection is now complete, with the watermain installation extending nearly one-third of the way between Elm Street and Main Street.
Next, crews will focus on Mountain Street between Elm Street and Main Street. Starting Monday, October 19, this section will be fully closed to through traffic for approximately four to six weeks. Detours will be in place, and while parking lots will not be accessible from Mountain Street, sidewalk access to businesses will be maintained throughout construction. Businesses will remain open throughout the closure.
And there's plenty to look forward to downtown! Join us this Saturday, October 17, for the Moonlight Market & Movie at Coronation Park from 6:00 p.m. to 9:00 p.m.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 19
Full Closure: Mountain Street (Elm Street to Main Street)
Starting Monday, October 19, for approximately four to six weeks
- Both crews will focus on watermain installation along Mountain Street between Elm Street and Main Street.
- This section of Mountain Street will be fully closed to through traffic.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
- Downtown parking lots remain accessible.
What to Expect: Hydro-Vac Excavation
Some of the work that will shape downtown's future happens underground. When crews need to work around existing utilities, a hydro-vac truck helps them dig more carefully.
- Pressurized water loosens the soil, and a vacuum removes it so crews can expose underground utilities without damaging them.
- Some sections will also be excavated by hand.
- This method is slower than standard excavation, which is why this phase is expected to take four to six weeks.
- See the full construction plan below.

Taking this time to work carefully around existing infrastructure is an important part of moving the project forward without interrupting the services the community relies on.
Detour Plan for Cars
Driving downtown? The local traffic plan shows the Mountain Street closure and the designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Click here for the full detour plan for cars
Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Click here for the full detour plan for heavy trucks
Please plan ahead, allow extra travel time and follow posted signage while crews complete this next phase of the Downtown Reimagined project.
Downtown Highlights
There's still plenty to enjoy downtown this fall! From seasonal events to community traditions, there's a reason to make downtown part of your plans.
- π Moonlight Market & Movie: Saturday, October 17, from 6:00 p.m. to 9:00 p.m. at Coronation Park.
- π» GrimsBOO! Halloween Event: returns to Downtown Grimsby on Saturday, October 24! Presented by Civiconnect, this free community event brings a day of Halloween fun to downtown, with activities running from 11 a.m. to 3 p.m.
- π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town, enjoy a glowing display of more than 300 carved jack-o'-lanterns, seasonal photo stations and light refreshments to wrap up spooky season!
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
Whether you're attending an event or visiting your favourite local business, we encourage you to keep exploring downtown and supporting the community that makes it special.
A LOOK BACK
Week of October 12 Construction Recap
This week, crews reached several milestones across the Downtown Reimagined project area.
On Main Street West, watermain work is complete, apart from final connections. On Elm Street, crews finished the remaining trench restoration.
At the Elm Street and Mountain Street intersection, the night crew completed its work and advanced the watermain nearly a third of the way through the section between Elm Street and Main Street.
Crews also cleared the Lions Pool parking lot on Friday, despite delays caused by a highway backup on Thursday, to prepare for this Saturday's Moonlight Market & Movie.
Each milestone brings the project forward while local businesses and community events continue to make downtown a place to gather and explore.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Downtown Grimsby is taking shape, one step at a time!
As work continues, crews are making progress on underground infrastructure while we keep downtown accessible for the people, businesses and experiences that make it special.
Watermain work on Main Street West is complete, apart from the final connections. Crews have also completed the remaining trench restoration on Elm Street. Overnight work at the Elm Street and Mountain Street intersection is now complete, with the watermain installation extending nearly one-third of the way between Elm Street and Main Street.
Next, crews will focus on Mountain Street between Elm Street and Main Street. Starting Monday, October 19, this section will be fully closed to through traffic for approximately four to six weeks. Detours will be in place, and while parking lots will not be accessible from Mountain Street, sidewalk access to businesses will be maintained throughout construction. Businesses will remain open throughout the closure.
And there's plenty to look forward to downtown! Join us this Saturday, October 17, for the Moonlight Market & Movie at Coronation Park from 6:00 p.m. to 9:00 p.m.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 19
Full Closure: Mountain Street (Elm Street to Main Street)
Starting Monday, October 19, for approximately four to six weeks
- Both crews will focus on watermain installation along Mountain Street between Elm Street and Main Street.
- This section of Mountain Street will be fully closed to through traffic.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
- Downtown parking lots remain accessible.
What to Expect: Hydro-Vac Excavation
Some of the work that will shape downtown's future happens underground. When crews need to work around existing utilities, a hydro-vac truck helps them dig more carefully.
- Pressurized water loosens the soil, and a vacuum removes it so crews can expose underground utilities without damaging them.
- Some sections will also be excavated by hand.
- This method is slower than standard excavation, which is why this phase is expected to take four to six weeks.
- See the full construction plan below.

Taking this time to work carefully around existing infrastructure is an important part of moving the project forward without interrupting the services the community relies on.
Detour Plan for Cars
Driving downtown? The local traffic plan shows the Mountain Street closure and the designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Click here for the full detour plan for cars
Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Click here for the full detour plan for heavy trucks
Please plan ahead, allow extra travel time and follow posted signage while crews complete this next phase of the Downtown Reimagined project.
Downtown Highlights
There's still plenty to enjoy downtown this fall! From seasonal events to community traditions, there's a reason to make downtown part of your plans.
- π Moonlight Market & Movie: Saturday, October 17, from 6:00 p.m. to 9:00 p.m. at Coronation Park.
- π» GrimsBOO! Halloween Event: returns to Downtown Grimsby on Saturday, October 24! Presented by Civiconnect, this free community event brings a day of Halloween fun to downtown, with activities running from 11 a.m. to 3 p.m.
- π Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town, enjoy a glowing display of more than 300 carved jack-o'-lanterns, seasonal photo stations and light refreshments to wrap up spooky season!
- π Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
Whether you're attending an event or visiting your favourite local business, we encourage you to keep exploring downtown and supporting the community that makes it special.
A LOOK BACK
Week of October 12 Construction Recap
This week, crews reached several milestones across the Downtown Reimagined project area.
On Main Street West, watermain work is complete, apart from final connections. On Elm Street, crews finished the remaining trench restoration.
At the Elm Street and Mountain Street intersection, the night crew completed its work and advanced the watermain nearly a third of the way through the section between Elm Street and Main Street.
Crews also cleared the Lions Pool parking lot on Friday, despite delays caused by a highway backup on Thursday, to prepare for this Saturday's Moonlight Market & Movie.
Each milestone brings the project forward while local businesses and community events continue to make downtown a place to gather and explore.

THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β October 13, 2026
Share Downtown Reimagined Project Update β October 13, 2026 on Facebook Share Downtown Reimagined Project Update β October 13, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β October 13, 2026 on Linkedin Email Downtown Reimagined Project Update β October 13, 2026 linkHope you had a great Thanksgiving weekend, Grimsby!
Crews encountered challenging ground conditions and difficulties connecting to existing sanitary infrastructure at Elm Street and Mountain Street last week. As a result, overnight work will resume Tuesday, October 13 at 8:00 p.m. and is expected to continue for the remainder of the week.
Meanwhile, watermain installation continues along Main Street West, where conflicts with existing Bell infrastructure have extended the construction timeline.
Here's what you need to know about this week's construction activities, traffic impacts and detours.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 12
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Continuing this week
- Watermain installation will continue along Main Street West. Crews are working around existing Bell infrastructure encased in concrete, which has delayed completion of this stage. Once complete, crews will move to Mountain Street between Elm Street and Main Street.Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours.
- The left-turn lane at Main Street West and Christie Street will remain closed.
- No detour is required.
- See the construction plan below.

Night Work: Elm Street and Mountain Street Intersection
Resuming Tuesday, October 13 at 8:00 p.m.
Overnight construction will resume Tuesday, October 13, from 8:00 p.m. to 6:00 a.m. Crews are expected to continue working overnight for the remainder of the week to maintain progress and avoid disruptions associated with switching between day and night shifts.
Traffic impacts:
- The intersection will be closed to through traffic overnight from 8:00 p.m. to 6:00 a.m.
- The intersection is expected to reopen each morning at approximately 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots will remain accessible.
- See the construction plan graphic below.

Detour Plans
Detours will be in place whenever the intersection is closed, including during overnight construction and the upcoming Mountain Street closure.
Residents and businesses on Elm Street and Mountain Street will remain accessible to local traffic, but through traffic will not be permitted at the intersection.
Detour Plan for Cars

Click for the full detour plan for cars
Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, please follow the designated truck detour (graphic below).

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you're downtown, you can check out:
π Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
π» GrimsBOO! Halloween Event: Saturday, October 24.
π Santa Claus Parade: Saturday, December 5 at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
A LOOK BACK
Week of October 5 Construction Recap
Last week, crews made progress in two key construction areas:

Watermain Installation: Main Street West
Crews continued watermain installation along Main Street West, working through challenges associated with existing underground Bell infrastructure.
Night Work: Elm Street and Mountain Street Intersection
Crews worked overnight Wednesday, Thursday and Friday on sanitary infrastructure connections at the intersection. Despite challenging ground conditions, work progressed and will continue this week.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Hope you had a great Thanksgiving weekend, Grimsby!
Crews encountered challenging ground conditions and difficulties connecting to existing sanitary infrastructure at Elm Street and Mountain Street last week. As a result, overnight work will resume Tuesday, October 13 at 8:00 p.m. and is expected to continue for the remainder of the week.
Meanwhile, watermain installation continues along Main Street West, where conflicts with existing Bell infrastructure have extended the construction timeline.
Here's what you need to know about this week's construction activities, traffic impacts and detours.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 12
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Continuing this week
- Watermain installation will continue along Main Street West. Crews are working around existing Bell infrastructure encased in concrete, which has delayed completion of this stage. Once complete, crews will move to Mountain Street between Elm Street and Main Street.Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours.
- The left-turn lane at Main Street West and Christie Street will remain closed.
- No detour is required.
- See the construction plan below.

Night Work: Elm Street and Mountain Street Intersection
Resuming Tuesday, October 13 at 8:00 p.m.
Overnight construction will resume Tuesday, October 13, from 8:00 p.m. to 6:00 a.m. Crews are expected to continue working overnight for the remainder of the week to maintain progress and avoid disruptions associated with switching between day and night shifts.
Traffic impacts:
- The intersection will be closed to through traffic overnight from 8:00 p.m. to 6:00 a.m.
- The intersection is expected to reopen each morning at approximately 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots will remain accessible.
- See the construction plan graphic below.

Detour Plans
Detours will be in place whenever the intersection is closed, including during overnight construction and the upcoming Mountain Street closure.
Residents and businesses on Elm Street and Mountain Street will remain accessible to local traffic, but through traffic will not be permitted at the intersection.
Detour Plan for Cars

Click for the full detour plan for cars
Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, please follow the designated truck detour (graphic below).

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you're downtown, you can check out:
π Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
π» GrimsBOO! Halloween Event: Saturday, October 24.
π Santa Claus Parade: Saturday, December 5 at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
A LOOK BACK
Week of October 5 Construction Recap
Last week, crews made progress in two key construction areas:

Watermain Installation: Main Street West
Crews continued watermain installation along Main Street West, working through challenges associated with existing underground Bell infrastructure.
Night Work: Elm Street and Mountain Street Intersection
Crews worked overnight Wednesday, Thursday and Friday on sanitary infrastructure connections at the intersection. Despite challenging ground conditions, work progressed and will continue this week.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Downtown Reimagined Project Update β October 2, 2026
Share Downtown Reimagined Project Update β October 2, 2026 on Facebook Share Downtown Reimagined Project Update β October 2, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update β October 2, 2026 on Linkedin Email Downtown Reimagined Project Update β October 2, 2026 linkThere’s been a lot of movement across downtown this week!
Paving is now complete on Main Street East and the majority of Elm Street, allowing Elm Street to fully reopen. Watermain installation was also completed on Rossmore Avenue and installation began on Main Street West, west of Forty Mile Creek.
And that’s a wrap on the Construction Passport! Thank you to everyone who participated, collected stamps and showed their support for downtown businesses along the way.
Keep reading for a quick look at what’s ahead for the week of October 5, plus a recap of this week’s construction milestones.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 5
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Expected completion by the end of the week of October 5
- Watermain installation will continue along Main Street West. The servicing crew will move to this area early to mid-week once work on Rossmore Avenue is complete.
- Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours. The left-turn lane at Main Street West and Christie Street will remain closed.
- See the traffic plan below.

Night Work: Elm Street and Mountain Street Intersection
Tentatively starting Wednesday, October 7 at 8:00 p.m.
Construction Plan
- Crews will complete work at the intersection overnight from Wednesday, October 7 until Saturday, October 10, starting at 8:00 p.m. in the evening until 6:00 a.m. the next day. The intersection will reopen each morning at approximately 6:00 a.m.
- Soil from the night work will be temporarily stockpiled at the pool parking lot, as receiving sites are not open overnight.
- The intersection will be closed to through traffic from 8:00 p.m. to 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots remain accessible.
- Once the intersection work is complete, Mountain Street between Elm Street and Main Street will be fully closed for approximately four weeks so crews can complete the work during the daytime.
- See the construction plan graphic below.

Detour Plans
The detours will be in place whenever the intersection is closed: overnight from 8:00 p.m. to 6:00 a.m. during the night work, and around the clock during the full closure of Mountain Street.
Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways. Residents and businesses on these streets can still be reached, but there will be no through traffic at the intersection. See the detour plan for cars graphic below.

Click for the full detour plan for cars
For heavy trucks travelling between Mountain Road and the QEW, please see the detour plan for trucks graphic below.

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you’re downtown, you can check out:
- π Grimsby Farmers’ Market: Final market of the season! Thursday, October 8 at the Major Refrigeration Peach King Centre behind Town Hall.
- π Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
A LOOK BACK
Week of September 28 Construction Recap
This week brought several construction milestones across the Downtown Reimagined project area.
Paving: Main Street East and Elm Street
Overnight paving along Main Street East, through the Elm Street intersection and into the Balsam Lane parking lot, wrapped up Wednesday morning. Daytime crews then completed pavement restoration along the majority of Elm Street by the end of Thursday, allowing Elm Street to fully reopen.
A small section of the mainline trench near Oak Street remains to be restored and will be completed when Mountain Street is paved following watermain installation.
Watermain Installation: Rossmore Avenue
Directional drilling for the watermain was completed on Rossmore Avenue this week. The last service and hydrant will be installed early next week, and all that will remain is the final connections, which will be scheduled at a later date.
Watermain Installation: Main Street West
Watermain installation began Wednesday on Main Street West, west of Forty Mile Creek. Crews will continue west toward just beyond Patton Street next week.
Soil Stockpile: Pool Parking Lot
The soil stockpile at the pool parking lot was fully removed Friday. The area will be used temporarily for additional stockpiling associated with upcoming night work at the Mountain Street intersections, with material removed shortly after it is placed.
Construction Passport Wrapped
The Construction Passport has officially wrapped! Thank you to everyone who picked up a passport, collected stamps and supported downtown businesses throughout construction.
THANK YOU FOR YOUR PATIENCE
We recognize that a project of this scale brings temporary changes to daily routines. Our goal is to provide clear and timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience, partnership and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! If you haven’t already subscribed to the project news page, simply select “Follow Project” on the right-hand side of the page.
Follow Downtown Reimagined
Visit www.letstalkgrimsby.ca/dr-construction and select “Follow Project” to receive updates directly in your inbox.
And be sure to follow our official Facebook and Instagram channels!
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
There’s been a lot of movement across downtown this week!
Paving is now complete on Main Street East and the majority of Elm Street, allowing Elm Street to fully reopen. Watermain installation was also completed on Rossmore Avenue and installation began on Main Street West, west of Forty Mile Creek.
And that’s a wrap on the Construction Passport! Thank you to everyone who participated, collected stamps and showed their support for downtown businesses along the way.
Keep reading for a quick look at what’s ahead for the week of October 5, plus a recap of this week’s construction milestones.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 5
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Expected completion by the end of the week of October 5
- Watermain installation will continue along Main Street West. The servicing crew will move to this area early to mid-week once work on Rossmore Avenue is complete.
- Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours. The left-turn lane at Main Street West and Christie Street will remain closed.
- See the traffic plan below.

Night Work: Elm Street and Mountain Street Intersection
Tentatively starting Wednesday, October 7 at 8:00 p.m.
Construction Plan
- Crews will complete work at the intersection overnight from Wednesday, October 7 until Saturday, October 10, starting at 8:00 p.m. in the evening until 6:00 a.m. the next day. The intersection will reopen each morning at approximately 6:00 a.m.
- Soil from the night work will be temporarily stockpiled at the pool parking lot, as receiving sites are not open overnight.
- The intersection will be closed to through traffic from 8:00 p.m. to 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots remain accessible.
- Once the intersection work is complete, Mountain Street between Elm Street and Main Street will be fully closed for approximately four weeks so crews can complete the work during the daytime.
- See the construction plan graphic below.

Detour Plans
The detours will be in place whenever the intersection is closed: overnight from 8:00 p.m. to 6:00 a.m. during the night work, and around the clock during the full closure of Mountain Street.
Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways. Residents and businesses on these streets can still be reached, but there will be no through traffic at the intersection. See the detour plan for cars graphic below.

Click for the full detour plan for cars
For heavy trucks travelling between Mountain Road and the QEW, please see the detour plan for trucks graphic below.

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you’re downtown, you can check out:
- π Grimsby Farmers’ Market: Final market of the season! Thursday, October 8 at the Major Refrigeration Peach King Centre behind Town Hall.
- π Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
A LOOK BACK
Week of September 28 Construction Recap
This week brought several construction milestones across the Downtown Reimagined project area.
Paving: Main Street East and Elm Street
Overnight paving along Main Street East, through the Elm Street intersection and into the Balsam Lane parking lot, wrapped up Wednesday morning. Daytime crews then completed pavement restoration along the majority of Elm Street by the end of Thursday, allowing Elm Street to fully reopen.
A small section of the mainline trench near Oak Street remains to be restored and will be completed when Mountain Street is paved following watermain installation.
Watermain Installation: Rossmore Avenue
Directional drilling for the watermain was completed on Rossmore Avenue this week. The last service and hydrant will be installed early next week, and all that will remain is the final connections, which will be scheduled at a later date.
Watermain Installation: Main Street West
Watermain installation began Wednesday on Main Street West, west of Forty Mile Creek. Crews will continue west toward just beyond Patton Street next week.
Soil Stockpile: Pool Parking Lot
The soil stockpile at the pool parking lot was fully removed Friday. The area will be used temporarily for additional stockpiling associated with upcoming night work at the Mountain Street intersections, with material removed shortly after it is placed.
Construction Passport Wrapped
The Construction Passport has officially wrapped! Thank you to everyone who picked up a passport, collected stamps and supported downtown businesses throughout construction.
THANK YOU FOR YOUR PATIENCE
We recognize that a project of this scale brings temporary changes to daily routines. Our goal is to provide clear and timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience, partnership and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! If you haven’t already subscribed to the project news page, simply select “Follow Project” on the right-hand side of the page.
Follow Downtown Reimagined
Visit www.letstalkgrimsby.ca/dr-construction and select “Follow Project” to receive updates directly in your inbox.
And be sure to follow our official Facebook and Instagram channels!
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Week of September 28: Main Street East and Elm Street Paving Update
Share Week of September 28: Main Street East and Elm Street Paving Update on Facebook Share Week of September 28: Main Street East and Elm Street Paving Update on X (formerly Twitter) Share Week of September 28: Main Street East and Elm Street Paving Update on Linkedin Email Week of September 28: Main Street East and Elm Street Paving Update linkPaving work on Main Street East is now complete, and through traffic was restored at approximately 6:30 a.m. Tuesday, September 29.
Crews are now focused on completing the remaining paving work on Elm Street, including sections near the Oak Street intersection and surrounding areas, as well as remaining cross trenches.
Based on current progress, daytime paving work on Elm Street is expected to continue through the remainder of this week.
What to expect
- One lane will remain open during daytime paving operations.
- Drivers should expect lane restrictions, slower traffic and delays while crews are working on Elm Street.
- Temporary access restrictions may be required as paving progresses, but access to local businesses and properties will be maintained where possible.
- Work will continue through the week, weather and site conditions permitting.
- See construction plan graphic below.

Click here for the construction plan
We recognize the ongoing impacts this construction has had on residents, businesses and visitors, and appreciate your patience as crews complete the remaining paving work on Elm Street.
Updates will be provided as work progresses.
NEXT STEPS
We recognize that a project of this scale brings temporary changes to daily routines, and we remain committed to providing clear, timely communication throughout construction.
Our goal is to make this process as predictable and manageable as possible while delivering long-term improvements that will benefit residents, businesses, and visitors for generations to come.
Thank you for your continued patience, partnership, and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! If you haven’t already subscribed to the project news page, simply select “Follow Project” on the right-hand side of the page.
Follow Downtown Reimagined
Visit www.letstalkgrimsby.ca/dr-construction and select “Follow Project” to receive updates directly in your inbox.
And be sure to follow our official Facebook and Instagram channels!
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
Paving work on Main Street East is now complete, and through traffic was restored at approximately 6:30 a.m. Tuesday, September 29.
Crews are now focused on completing the remaining paving work on Elm Street, including sections near the Oak Street intersection and surrounding areas, as well as remaining cross trenches.
Based on current progress, daytime paving work on Elm Street is expected to continue through the remainder of this week.
What to expect
- One lane will remain open during daytime paving operations.
- Drivers should expect lane restrictions, slower traffic and delays while crews are working on Elm Street.
- Temporary access restrictions may be required as paving progresses, but access to local businesses and properties will be maintained where possible.
- Work will continue through the week, weather and site conditions permitting.
- See construction plan graphic below.

Click here for the construction plan
We recognize the ongoing impacts this construction has had on residents, businesses and visitors, and appreciate your patience as crews complete the remaining paving work on Elm Street.
Updates will be provided as work progresses.
NEXT STEPS
We recognize that a project of this scale brings temporary changes to daily routines, and we remain committed to providing clear, timely communication throughout construction.
Our goal is to make this process as predictable and manageable as possible while delivering long-term improvements that will benefit residents, businesses, and visitors for generations to come.
Thank you for your continued patience, partnership, and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! If you haven’t already subscribed to the project news page, simply select “Follow Project” on the right-hand side of the page.
Follow Downtown Reimagined
Visit www.letstalkgrimsby.ca/dr-construction and select “Follow Project” to receive updates directly in your inbox.
And be sure to follow our official Facebook and Instagram channels!
@downtownreimaginedQuestions?
Email DTreimagined@grimsby.ca
-
Email DTreimagined@grimsby.ca -
Email DTreimagined@grimsby.ca -
Email DTreimagined@grimsby.ca -
-
-
Phase 1 - Visioning Study
Downtown Reimagined Construction Phase has finished this stageTown commissioned study/visioning exercise to work with the community and stakeholders to provide an updated vision for Downtown. Phase 1 Produced:
- Parking Study
- Traffic Study
- Design Guidelines
- Design Concept Plan
-
Phase 2 - Detailed Design
Downtown Reimagined Construction Phase has finished this stageThe Town has commissioned CIMA+ to complete the detailed design and this process is currently underway. The design concept identified key elements such as:
Road Cross Section- Narrower Road
- Wider sidewalks
- Parking strategy
- Landscape/furnishing zone
Prioritized elements- Trees & plantings
- Landscaping
- Furniture
- Public art
- Lighting
- Active & inviting storefronts
TIMING: January - September 2026
-
Phase 3 - Construction Stage 1 (2026)
Downtown Reimagined Construction Phase is currently at this stageUnderground Work (outside of downtown core).
Focus is Watermain and Sewer.
Current estimated timelines for construction are:
January - February 2026
- Design Completion
February - April 2026
- Contractor Pricing & Award
May - November 2026
- Construction outside of downtown core - (Streets include: Elm, Mountain/Christie, Main - West of Mountain and East of Elm, and Rossmore).
Work includes:
- Watermain replacement
- Sanitary sewer repair (re-lining)
- Sanitary lateral replacement
- Road restoration
While every effort is made to keep timelines accurate, dates shown on this page may change as the project progresses due to unforeseen circumstances or unexpected challenges.
-
Phase 3 - Construction Stage 2 (2026 / 2027)
this is an upcoming stage for Downtown Reimagined Construction PhaseDowntown Core to be completed.
Focus is on road, watermain and sewer.
November 2026 - February 2027
- Contractor Pricing & Award for road and underground work.
April - August 2027
- Road, watermain and sewer work to be completed in downtown core.
Work includes:
- Watermain replacement
- Storm sewer installation
- Sanitary sewer repair (re-lining)
- Sanitary lateral replacement
- Full road reconstruction
While every effort is made to keep timelines accurate, dates shown on this page may change as the project progresses due to unforeseen circumstances or unexpected challenges.
- What is the Downtown Reimagined project?
- Why is this project necessary?
- What improvements will we see above ground?
- How is the Town supporting local businesses during construction?
- How will residents be impacted during construction?
- Will vehicular traffic still be allowed?
- How will emergency access be maintained?
- How will traffic be affected during construction?
- What does βpedestrian-priorityβ mean for downtown?
- Will the new design reflect Grimsbyβs heritage and identity?
- How can residents and businesses stay informed?
- How will feedback be collected?
- Did the Public have an opportunity to review the design before construction?
- How long will construction last?
- Will the Downtown Grimsby Reimagined Project improve wheelchair accessibility to local businesses?
-
2026-09-10 - Detour Plan - Night Work Extended.pdf (377 KB) (pdf)
-
2026-09-10 - Traffic Plan - Night Work Extended.pdf (475 KB) (pdf)
-
2026-09-04 - DTR Phase 1 - Detour Plan - Week of Sept 8.jpg (359 KB) (jpg)
-
2026-09-04 - DTR Phase 1 - Traffic Plan - Week of Sept 8.jpg (382 KB) (jpg)
-
2026-08-28 - DTR Phase 1 - Detour Plan - Week of Aug 31.pdf (991 KB) (pdf)
-
2026-08-28 - DTR Phase 1 - Construction Process - Week of Aug 31.pdf (330 KB) (pdf)
-
2026-08-21 - DTR Phase 1 - Road Map .pdf (494 KB) (pdf)
-
2026-07-31 - DTR Phase 1 - Road Map - Week of Aug 17.pdf (825 KB) (pdf)
-
2026-07-31 - DTR Phase 1 - Road Map - Week of Aug 10.pdf (543 KB) (pdf)
-
2026-07-31 - DTR Phase 1 - Road Map - Week of July 31.pdf (536 KB) (pdf)
-
July 24 Traffic Plan.pdf (265 KB) (pdf)
-
July 17 - Traffic Plan (1 page).pdf (619 KB) (pdf)
-
July 10 - Traffic Plan (1 page) - V0 Final.pdf (1.49 MB) (pdf)
-
July 3 - Construction Plan (1 page) - V1 Final.pdf (394 KB) (pdf)
-
July 3 - Traffic Plan (1 page) - V0 Final.pdf (735 KB) (pdf)
-
June 26 - Construction Plan (1 page) - V0 FINAL.pdf (445 KB) (pdf)
-
June 26 - Traffic Plan (1 page) - V0 FINAL.pdf (985 KB) (pdf)
-
June 22 - Sequence of Construction (1 page) - V1 FINAL.pdf (1.47 MB) (pdf)
-
June 22 - Staging and Project Signage (2 pages) - V1 FINAL.pdf (1.46 MB) (pdf)
-
What We Heard_Downtown Business Meeting on Dec 4 2025.docx (1.97 MB) (docx)
-
Downtown Reimagined Public Information Centre. Nov 30_ 2023.pdf (8.77 MB) (pdf)
-
Town of Grimsby Urban Design Guidelines.pdf (4.24 MB) (pdf)
-
Downtown Reimagined Project Update Detailed Presentation_Dec. 4_2025.pdf (9.74 MB) (pdf)
-
Press Release_The Town of Grimsby Breaks Ground on Downtown Reimagined Backed by 1.9M Joint Federal and Provincial Investment.pdf (98.1 KB) (pdf)
-
2026-09-11 - Detour Plan - Night Work Extended.pdf (377 KB) (pdf)
-
2026-09-11 - DTR Phase 1 - Updated Staging Plan.pdf (477 KB) (pdf)
-
2026-09-11 - Traffic Plan - Night Work Extended.pdf (491 KB) (pdf)
-
2026-09-11 - Detour Plan - Night Work Extended.pdf (451 KB) (pdf)
-
2026-09-18 - Detour Plan - Night Work Extended.pptx.pdf (451 KB) (pdf)
-
2026-09-18 - Traffic Plan - Night Work Extended.pptx.pdf (549 KB) (pdf)
-
2026-09-24 - 24hr Paving Map.pdf (466 KB) (pdf)
-
2026-09-25 - Traffic Plan - Rossmore Ave.pdf (476 KB) (pdf)
-
2026-09-25 - Traffic Plan - Main Street West.pdf (462 KB) (pdf)
-
2026-09-29 - Paving Plan - Elm Street.pdf (409 KB) (png)
-
2026-09-25 - Car Detour Plan - Mountain and Elm Intersection.png (649 KB) (png)
-
2026-09-25 - Traffic Plan - Mountain and Elm Intersection.png (558 KB) (png)
-
2026-09-25 - Truck Detour Plan - Mountain and Elm Intersection.png (683 KB) (png)
-
2026-10-05 - Traffic Plan - Main St.png (521 KB) (png)
-
Oct 12_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
DETOUR_STAGE04_Oct 12.png (649 KB) (png)
-
Traffic Plan - Oct 12-Mountain and Elm Intersection.png (558 KB) (png)
-
TRAFFIC_Patton_Oct 12.png (529 KB) (png)
-
Oct 19_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
Oct-19-Detour-Plan-Mountain St.png (537 KB) (png)
-
Oct 19-Traffic-Plan-Mountain-St.png (498 KB) (png)
-
Oct 26_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
Oct-26-Detour-Plan-Mountain St.png (537 KB) (png)
-
Oct 26-Traffic-Plan-Mountain-St.png (499 KB) (png)
-
Oct 26_DETOUR Plan_Intersection of Christie St Mountain St and Main St West.png.png (646 KB) (png)
-
Oct 26_TRAFFIC PLAN_Intersection of Christie St Mountain St and Main St West.png (518 KB) (png)
-
2026-10-23 - Commissioning Process.jpg (1.07 MB) (jpg)
-
Nov 02_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
Nov-02-Detour-Plan-Mountain St.png (537 KB) (png)
-
Nov 02-Traffic-Plan-Mountain-St.png (498 KB) (png)
-
11-04-2026_Christie Street Parking Lot.png (4.62 MB) (png)
-
Nov 09-Traffic-Plan-Mountain-St.png (498 KB) (png)
-
Nov-09-Detour-Plan-Mountain St.png (537 KB) (png)
-
Nov 09_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
Nov 16-Traffic-Plan-Mountain-St.png (498 KB) (png)
-
Nov-16-Detour-Plan-Mountain St.png (536 KB) (png)
-
Nov 16_DETOUR PLAN (TRUCKS)-Intersection-Hamilton-Grimsby-Vineland .png (692 KB) (png)
-
Construction-Look-Ahead-Nov-16_updated.png (375 KB) (png)


@downtownreimagined
@downtownreimagined
@downtownreimagined