Downtown Reimagined Project Update – October 2, 2026
There’s been a lot of movement across downtown this week!
Paving is now complete on Main Street East and the majority of Elm Street, allowing Elm Street to fully reopen. Watermain installation was also completed on Rossmore Avenue and installation began on Main Street West, west of Forty Mile Creek.
And that’s a wrap on the Construction Passport! Thank you to everyone who participated, collected stamps and showed their support for downtown businesses along the way.
Keep reading for a quick look at what’s ahead for the week of October 5, plus a recap of this week’s construction milestones.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 5
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Expected completion by the end of the week of October 5
- Watermain installation will continue along Main Street West. The servicing crew will move to this area early to mid-week once work on Rossmore Avenue is complete.
- Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours. The left-turn lane at Main Street West and Christie Street will remain closed.
- See the traffic plan below.

Night Work: Elm Street and Mountain Street Intersection
Tentatively starting Wednesday, October 7 at 8:00 p.m.
Construction Plan
- Crews will complete work at the intersection overnight from Wednesday, October 7 until Saturday, October 10, starting at 8:00 p.m. in the evening until 6:00 a.m. the next day. The intersection will reopen each morning at approximately 6:00 a.m.
- Soil from the night work will be temporarily stockpiled at the pool parking lot, as receiving sites are not open overnight.
- The intersection will be closed to through traffic from 8:00 p.m. to 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots remain accessible.
- Once the intersection work is complete, Mountain Street between Elm Street and Main Street will be fully closed for approximately four weeks so crews can complete the work during the daytime.
- See the construction plan graphic below.

Detour Plans
The detours will be in place whenever the intersection is closed: overnight from 8:00 p.m. to 6:00 a.m. during the night work, and around the clock during the full closure of Mountain Street.
Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways. Residents and businesses on these streets can still be reached, but there will be no through traffic at the intersection. See the detour plan for cars graphic below.

Click for the full detour plan for cars
For heavy trucks travelling between Mountain Road and the QEW, please see the detour plan for trucks graphic below.

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you’re downtown, you can check out:
- 🍑 Grimsby Farmers’ Market: Final market of the season! Thursday, October 8 at the Major Refrigeration Peach King Centre behind Town Hall.
- 🎃 Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
A LOOK BACK
Week of September 28 Construction Recap
This week brought several construction milestones across the Downtown Reimagined project area.
Paving: Main Street East and Elm Street
Overnight paving along Main Street East, through the Elm Street intersection and into the Balsam Lane parking lot, wrapped up Wednesday morning. Daytime crews then completed pavement restoration along the majority of Elm Street by the end of Thursday, allowing Elm Street to fully reopen.
A small section of the mainline trench near Oak Street remains to be restored and will be completed when Mountain Street is paved following watermain installation.
Watermain Installation: Rossmore Avenue
Directional drilling for the watermain was completed on Rossmore Avenue this week. The last service and hydrant will be installed early next week, and all that will remain is the final connections, which will be scheduled at a later date.
Watermain Installation: Main Street West
Watermain installation began Wednesday on Main Street West, west of Forty Mile Creek. Crews will continue west toward just beyond Patton Street next week.
Soil Stockpile: Pool Parking Lot
The soil stockpile at the pool parking lot was fully removed Friday. The area will be used temporarily for additional stockpiling associated with upcoming night work at the Mountain Street intersections, with material removed shortly after it is placed.
Construction Passport Wrapped
The Construction Passport has officially wrapped! Thank you to everyone who picked up a passport, collected stamps and supported downtown businesses throughout construction.
THANK YOU FOR YOUR PATIENCE
We recognize that a project of this scale brings temporary changes to daily routines. Our goal is to provide clear and timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience, partnership and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! If you haven’t already subscribed to the project news page, simply select “Follow Project” on the right-hand side of the page.
Follow Downtown Reimagined
Visit www.letstalkgrimsby.ca/dr-construction and select “Follow Project” to receive updates directly in your inbox.
And be sure to follow our official Facebook and Instagram channels!
@downtownreimagined
Questions?
Email DTreimagined@grimsby.ca
@downtownreimagined
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends