Downtown Reimagined Project Update – November 6, 2026

This week, crews worked both day and night shifts to complete the remaining watermain and service work along Main Street and Christie Street. With work on Christie Street now complete, all sections of the project's new watermain have officially been installed! This marks a significant achievement and another exciting step forward in the transformation of our downtown. The next step is to complete the remaining mainline and service connections throughout the project area. Crews will connect the newly installed pipes to the existing watermain system and individual properties, bringing us another step closer to completing this important infrastructure upgrade.

The new watermains on Elm Street, Main Street East and Rossmore Avenue also successfully passed their pressure tests this week. This important milestone clears the way for disinfection and bacteria testing to begin next week, with final connections to follow.

Crews also started repairing sanitary laterals on Mountain Street between Elm Street and Main Street.

Next week, both crews will return to day shifts, focusing on completing the remaining sanitary lateral repairs on Mountain Street. This work is expected to wrap up by the end of next week. In the meantime, Mountain Street between Elm Street and Main Street will remain closed to through traffic, with the existing detour in place.

Beginning Thursday night, crews will also start swabbing the remaining sections of new watermain on Mountain Street, Main Street and Christie Street, followed by pressure testing.

Another exciting milestone is just around the corner! Weather permitting, paving will begin Sunday night, November 15, and is expected to take about two shifts. To accommodate this work, the intersection of Main Street and Christie Street will be closed overnight from 8:00 p.m. to 7:00 a.m., beginning Sunday, November 15, until paving is complete. Mountain Street is expected to reopen once paving is complete.

Calling all young artists! There's still time to enter the Mayor's Holiday Greeting Card Contest, with submissions due Friday, November 13, at 4:30 p.m. And the holiday season is just around the corner, with the Town Tree Lighting and Fantasy of Trees both kicking off November 26.

THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 9

Full Closure Continues: Mountain Street, between Elm Street and Main Street

Resumes Monday, November 9

  • Both crews will work day shifts to finish sanitary lateral repairs in this section.
  • This work is expected to be complete by the end of the week.
  • Mountain Street remains fully closed to through traffic, with the same detour in place.
  • Mountain Street will reopen once paving on Main Street West and Christie Street is complete.
  • Cars must follow the designated detour shown on the local traffic plan.
  • Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
  • See construction plan graphic below.

Click here for the full plan

Detour Plan for Cars: Mountain Street Closure

Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Click here for the full plan

Detour Plan for Heavy Trucks

For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night paving closure at Main Street and Christie Street.

  • Hamilton: Red Hill Valley Parkway and Mud Street West.
  • Grimsby: Mountain Road and Mud Street East/West.
  • Vineland: Victoria Avenue and Fly Road.

Refer to the map for the appropriate route for your direction of travel.

Click here for the full plan

Watermain Swabbing and Pressure Testing: Mountain Street, Main Street and Christie Street

Starting Thursday, November 12

  • Crews will swab (clean) the remaining new watermain on Mountain, Main, and Christie Streets.
  • Pressure testing will follow.

Night Closure for Paving: Main Street and Christie Street Intersection

Starting Sunday, November 15, at 8:00 p.m.

  • Weather permitting, crews will pave Main Street West and Christie Street. Paving is expected to take about two shifts.
  • The intersection will be closed overnight from 8:00 p.m. to 7:00 a.m. until paving is complete.
  • The intersection will reopen each morning at 7:00 a.m.
  • Cars must follow the designated night closure detour.
  • Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Watermain Commissioning

The new watermains on Elm Street, Main Street East and Rossmore Avenue passed their pressure tests this week. Next, crews will disinfect these pipes and complete bacteria testing to confirm the water is safe. Once testing is complete, crews will make the final connections to the existing watermains and private services.

As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.

Downtown Highlights

There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.

  • 🎨 Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
  • 🎄 Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
  • 🌲 Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
  • 🎅 Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
  • 🛍️ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.

Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!

A LOOK BACK

Week of November 2 Construction Recap

This week brought two major watermain milestones across the project area.

On Main Street and Christie Street, one crew worked days and the other worked nights to finish the remaining watermain and service work. Work in this area is now complete, except for the final watermain and service connections.

With Christie Street done, all of the new watermain on the project has now been installed. The remaining work is limited to mainline and service connections throughout the project area, where crews will connect the new pipe to the existing watermains and private services.

On Elm Street, Main Street East and Rossmore Avenue, the new watermains passed their pressure tests. This is a significant step that allows disinfection and bacteria testing to begin next week.

On Mountain Street, crews started sanitary lateral repairs between Elm Street and Main Street at the end of the week. This work continues next week.

THANK YOU FOR YOUR PATIENCE

We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.

Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.

STAY CONNECTED

Project News and Updates

Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.

Follow Downtown Reimagined

Stay connected through our official Facebook and Instagram channels:
@downtownreimagined

@downtownreimagined

Questions?

Email DTreimagined@grimsby.ca

Share Downtown Reimagined Project Update – November 6, 2026 on Facebook Share Downtown Reimagined Project Update – November 6, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update – November 6, 2026 on Linkedin Email Downtown Reimagined Project Update – November 6, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>