Downtown Reimagined Project Update – October 13, 2026
Hope you had a great Thanksgiving weekend, Grimsby!
Crews encountered challenging ground conditions and difficulties connecting to existing sanitary infrastructure at Elm Street and Mountain Street last week. As a result, overnight work will resume Tuesday, October 13 at 8:00 p.m. and is expected to continue for the remainder of the week.
Meanwhile, watermain installation continues along Main Street West, where conflicts with existing Bell infrastructure have extended the construction timeline.
Here's what you need to know about this week's construction activities, traffic impacts and detours.
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 12
Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)
Continuing this week
- Watermain installation will continue along Main Street West. Crews are working around existing Bell infrastructure encased in concrete, which has delayed completion of this stage. Once complete, crews will move to Mountain Street between Elm Street and Main Street.Traffic impacts: One lane of alternating two-way traffic will be maintained during daytime work hours.
- The left-turn lane at Main Street West and Christie Street will remain closed.
- No detour is required.
- See the construction plan below.

Night Work: Elm Street and Mountain Street Intersection
Resuming Tuesday, October 13 at 8:00 p.m.
Overnight construction will resume Tuesday, October 13, from 8:00 p.m. to 6:00 a.m. Crews are expected to continue working overnight for the remainder of the week to maintain progress and avoid disruptions associated with switching between day and night shifts.
Traffic impacts:
- The intersection will be closed to through traffic overnight from 8:00 p.m. to 6:00 a.m.
- The intersection is expected to reopen each morning at approximately 6:00 a.m.
- Elm Street and Mountain Street will remain accessible to local traffic only, as dead-end roadways.
- Downtown parking lots will remain accessible.
- See the construction plan graphic below.

Detour Plans
Detours will be in place whenever the intersection is closed, including during overnight construction and the upcoming Mountain Street closure.
Residents and businesses on Elm Street and Mountain Street will remain accessible to local traffic, but through traffic will not be permitted at the intersection.
Detour Plan for Cars

Click for the full detour plan for cars
Detour Plan for Heavy Trucks
For heavy trucks travelling between Mountain Road and the QEW, please follow the designated truck detour (graphic below).

Click for the full detour plan for trucks
Downtown Highlights
Downtown remains open and accessible throughout construction. While you're downtown, you can check out:
🎃 Moonlight Market & Movie: Saturday, October 17 from 6:00 p.m. to 9:00 p.m. at Coronation Park!
👻 GrimsBOO! Halloween Event: Saturday, October 24.
🎅 Santa Claus Parade: Saturday, December 5 at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
A LOOK BACK
Week of October 5 Construction Recap
Last week, crews made progress in two key construction areas:

Watermain Installation: Main Street West
Crews continued watermain installation along Main Street West, working through challenges associated with existing underground Bell infrastructure.
Night Work: Elm Street and Mountain Street Intersection
Crews worked overnight Wednesday, Thursday and Friday on sanitary infrastructure connections at the intersection. Despite challenging ground conditions, work progressed and will continue this week.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimagined
Questions?
Email DTreimagined@grimsby.ca
@downtownreimagined
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends