Downtown Reimagined Project Update – October 30, 2026
There's been plenty happening in downtown Grimsby this week, and crews are continuing to make progress!
Both construction crews worked overnight at the Main Street and Christie Street intersection from Sunday to Thursday. Along the way, they encountered some unexpected underground obstacles, including buried trolley tracks and additional Bell infrastructure. Despite these discoveries, crews advanced to Forty Mile Creek and are now heading up Christie Street.
Another important milestone: watermain commissioning is officially underway! Swabbing took place Thursday night, with commissioning activities continuing next week.
For the week ahead, crews will divide their work between day and night shifts. Starting Sunday, November 1, at 8:00 p.m., the Main Street and Christie Street intersection will be closed overnight from 8:00 p.m. to 6:00 a.m., reopening each morning at 6:00 a.m. while the night crew installs hydrants and services.
Meanwhile, the day crew will install the final stretch of watermain on Christie Street, north of Main Street, up to the dead end of Elizabeth Street past the parking lot entrance. Once that's complete, crews will move on to installing the remaining sanitary laterals on Mountain Street between Elm Street and Main Street.
Mountain Street between Elm Street and Main Street remains closed to through traffic, with the same detour in place.
And that's a wrap on GrimsBOO! More than 1,000 kids trick-or-treated through downtown, bringing plenty of Halloween spirit to our local streets and businesses. Thank you to everyone who came out to celebrate!
And the community fun continues this weekend! Join the Grimsby Glows Pumpkin Parade on Sunday, November 1, at Coronation Park, then keep the creativity going on Monday, November 2, with a special art-making station at the Grimsby Public Art Gallery for the Mayor's Holiday Greeting Card Contest. It's a great opportunity for families to get out, take part and enjoy what's happening around town!
THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF NOVEMBER 2
Night Closure: Main Street and Christie Street Intersection
Starting Sunday, November 1st, at 8:00 p.m.
- The night crew will continue installing hydrants and services in the intersection.
- The intersection will be closed nightly from 8:00 p.m. to 6:00 a.m.
- The intersection will reopen every morning at 6:00 a.m.
- Cars must follow the designated night closure detour.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.
Daytime Work: Christie Street, North of Main Street
Starting Monday, November 2nd at 7:00 a.m.
- The day crew will install the final stretch of watermain north on Christie Street, up to the dead end of Elizabeth Street past the parking lot entrance.
- Please follow posted signage and traffic control.
Full Closure Continues: Mountain Street, between Elm Street and Main Street
Resumes Monday, November 2nd
- Mountain Street remains fully closed to through traffic, with the same detour in place.
- Once the Christie Street watermain is complete, crews will install the remaining sanitary laterals in this section.
- Cars must follow the designated detour shown on the local traffic plan.
- Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Detour Plan for Cars: Mountain Street Closure
Driving downtown? The local traffic plan shows the Mountain Street closure and designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Detour Plan for Heavy Trucks: Mountain Street Closure
For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.
- Hamilton: Red Hill Valley Parkway and Mud Street West.
- Grimsby: Mountain Road and Mud Street East/West.
- Vineland: Victoria Avenue and Fly Road.
Refer to the map for the appropriate route for your direction of travel.

Watermain Commissioning
Watermain commissioning began this week, with swabbing carried out Thursday night. Swabbing is the first step in cleaning newly installed watermains. Crews use large, bullet-shaped sponges, called swabs, which are pushed through the pipes with water to remove debris and sediment.
This is part of a broader testing process that includes pressure testing for leaks, disinfection with chlorine and water quality testing to ensure the pipes are safe before being connected to the active water distribution system.
Commissioning activities will continue next week.
As work continues, please plan ahead, allow extra travel time and follow posted signage and traffic control. We appreciate your patience and understanding as crews work through these important upgrades.
Downtown Highlights
There's lots happening in and around downtown as we head into the holiday season! Whether you're looking for a fun family outing or a chance to support local, here are a few upcoming events to add to your calendar.
- 🎃 Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town of Grimsby.
- 🎨 Mayor's Holiday Greeting Card Contest: Calling all young artists! Mayor Jeff Jordan and the Grimsby Public Art Gallery invite Grimsby youth aged 15 and under to design this year's holiday greeting card. Stop by the special art-making station outside the Gallery on Monday, November 2, to get creative! Submissions are due Friday, November 13, at 4:30 p.m. Learn more here.
- 🎄 Town Tree Lighting: Kick off the holiday season on Thursday, November 26, at 6 p.m. with the lighting of Grimsby's Town Tree, "Hope," outside Town Hall. Stay afterward for light refreshments and music inside Town Hall.
- 🌲 Fantasy of Trees: Get into the holiday spirit at the Grimsby Museum from November 26 to December 6! Enjoy a festive display of beautifully decorated Christmas trees, wreaths and seasonal décor, with proceeds supporting local charities. Admission is free! Open Tuesday to Friday, 10 a.m. to 8 p.m., and Saturday and Sunday, 10 a.m. to 5 p.m. (closed Mondays).
- 🎅 Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.
- 🛍️ Grimsby Museum Holiday Market: Shop local this holiday season! Visit the Grimsby Museum on Saturday, December 12, from 11 a.m. to 4 p.m. for its Holiday Market, featuring local makers, artisans and unique gift ideas.
Whether you're attending an event, grabbing a bite or visiting your favourite local business, there's plenty of reason to keep exploring downtown. We encourage everyone to continue showing our local businesses some love while work is underway!
A LOOK BACK
Week of October 26 Construction Recap
It's been a productive week on site, with crews working through some unexpected discoveries along the way.
At the Main Street and Christie Street intersection, both crews worked overnight from Sunday to Thursday. They encountered buried trolley tracks and additional Bell infrastructure, but continued making progress, advancing to Forty Mile Creek and now heading up Christie Street.
Watermain commissioning also got underway, with swabbing carried out Thursday night. This marks another important step in the project!

Construction Passport Winners
The wait is over! Construction Passport winners have been announced on the Downtown Grimsby BIA social channels, and the BIA has contacted all winners.
Congratulations to everyone who won, and a big thank you to everyone who participated and supported our downtown businesses along the way!
GrimsBOO! 2026 Recap
What a turnout! GrimsBOO! 2026 brought more than 1,000 kids trick-or-treating through downtown Grimsby, filling the streets with costumes, treats and plenty of Halloween spirit.
A huge thank you to the Downtown Grimsby BIA, participating businesses, volunteers, families and everyone who came out to celebrate. It was wonderful to see the community come together and support downtown!
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
@downtownreimagined
Questions?
Email DTreimagined@grimsby.ca

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends