Downtown Reimagined Project Update – October 23, 2026

Watermain work on Mountain Street is moving along.

This week, watermain installation on Mountain Street, between Elm Street and Main Street, advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection. The servicing crew has also made good progress installing services along this stretch.

Next week, night work resumes Sunday, October 25, at 8:00 p.m., crews will prepare the previously installed watermains for commissioning, with rolling lane closures along Elm Street and Main Street that night. Starting Monday night, October 26, the Main Street and Christie Street intersection will be closed from 8:00 p.m. to 6:00 a.m., reopening each morning for the rest of the week.

Mountain Street between Elm Street and Main Street remains fully closed while work in this section continues. With both crews on nights, you'll see minimal activity on site during the day. Crews return to day shifts in this area the following week.

Meanwhile, on Main Street West, paving between Forty Mile Creek and Patton Street is tentatively scheduled for Thursday, October 29. Watermain commissioning may also begin this week.

And there's plenty to look forward to downtown! GrimsBOO! takes over downtown this Saturday, October 24, from 11:00 a.m. to 3:00 p.m.

THE 60-SECOND RUN DOWN: WHAT YOU NEED TO KNOW FOR THE WEEK OF OCTOBER 26

Night Work and Full Closure at Mountain Street, between Elm Street and Main Street

Starting Sunday, October 25 at 8:00 p.m.

  • Crews will prepare the previously installed watermains for commissioning.
  • Expect rolling lane closures along Elm Street and Main Street overnight.
  • Please follow posted signage and traffic control.

Full Closure Continues: Mountain Street, between Elm Street and Main Street

  • Mountain Street remains fully closed to through traffic while work in this section continues.
  • Both crews will be on nights this week, so there will be minimal activity during the day.
  • Crews return to day shifts in this area the following week.
  • Cars must follow the designated detour shown on the local traffic plan.
  • Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Click here for the full plan

Detour Plan for Cars: Mountain Street Closure

Driving downtown? The local traffic plan shows the Mountain Street closure and the designated car detour around the work area. Follow the purple route shown on the map and posted detour signage.

Click here for the full plan

Detour Plan for Heavy Trucks

For heavy trucks travelling between Mountain Road and the QEW, use the designated regional truck detour routes shown in the map. This detour applies to both the Mountain Street closure and the night closure at Main Street and Christie Street.

  • Hamilton: Red Hill Valley Parkway and Mud Street West.
  • Grimsby: Mountain Road and Mud Street East/West.
  • Vineland: Victoria Avenue and Fly Road.

Refer to the map for the appropriate route for your direction of travel.

Click here for the full plan

Night Closure: Main Street and Christie Street Intersection

Starting Monday, October 26, for the rest of the week, from 8:00 p.m. to 6:00 a.m.

  • Crews will begin work in the Main Street and Christie Street intersection.
  • The intersection will be closed overnight starting 8:00 p.m.
  • The intersection reopens every morning at 6:00 a.m.
  • Cars must follow the designated night closure detour.
  • Heavy trucks travelling between Mountain Road and the QEW must follow the regional truck detour plan.

Click here for the full construction plan

Click here for the full detour plan

Please plan ahead, allow extra travel time and follow posted signage while crews complete this next phase of the Downtown Reimagined project.

Paving: Main Street West (Forty Mile Creek to Patton Street)

  • Paving is tentatively scheduled for Thursday, October 29.

What to Expect: Watermain Commissioning

Before the new watermains can go into service, they need to be checked.

  • Commissioning is the process of cleaning and testing the newly installed watermains before they are connected to the existing (live) watermain.
  • Commissioning may begin this week. We're waiting on confirmation from the sub-contractor and will share timing once it's confirmed.

Click here for the full plan

Downtown Highlights

Spooky season is here, and the holidays are right around the corner!

  • 👻 GrimsBOO! Halloween Event: Saturday, October 24, from 11:00 a.m. to 3:00 p.m. Presented by Civiconnect, this free community event brings a day of Halloween fun to downtown.

  • 🎃 Grimsby Glows Pumpkin Parade: Sunday, November 1, from 5:30 p.m. to 7:30 p.m. at Coronation Park (accessible start at 4:45 p.m.). Presented by the Rotary Club of Grimsby in collaboration with the Town, enjoy a glowing display of more than 300 carved jack-o'-lanterns, seasonal photo stations and light refreshments.

  • 🎅 Santa Claus Parade: Saturday, December 5, at 5:15 p.m. This year's theme is "Christmas Night of Lights." Float, walking group and volunteer applications are now open at grimsby.ca/parade.

Whether you're attending an event or visiting your favourite local business, we encourage you to keep exploring downtown and supporting the community that makes it special.

A LOOK BACK

Week of October 19 Construction Recap

This week, crews made strong progress on Mountain Street.

Between Elm Street and Main Street, watermain installation advanced quicker than anticipated and has reached the south side of the Main Street and Christie Street intersection.

The servicing crew also made good progress, installing services along the same stretch.

Each step forward brings the project closer to the next phase, while local businesses and community events continue to make downtown a place to gather and explore.

THANK YOU FOR YOUR PATIENCE

We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.

Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.

STAY CONNECTED

Project News and Updates

Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.

Follow Downtown Reimagined

Stay connected through our official Facebook and Instagram channels:


@downtownreimagined

@downtownreimagined


Questions?

Email DTreimagined@grimsby.ca

Share Downtown Reimagined Project Update – October 23, 2026 on Facebook Share Downtown Reimagined Project Update – October 23, 2026 on X (formerly Twitter) Share Downtown Reimagined Project Update – October 23, 2026 on Linkedin Email Downtown Reimagined Project Update – October 23, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>