Watermain work continues to move forward across Downtown Grimsby, with three new connections now complete and service connections underway on Elm Street.
There’s also an update to the Mountain Road reopening plan. Here’s a look at the latest construction progress, upcoming work and what residents and businesses can expect in the days ahead.
Watermain milestone: Three connections complete
The new watermain has now been connected to the existing system at three locations:
- Rossmore Avenue
- Robinson Street
- Kingsway Boulevard
These connections required temporary lane closures and traffic control due to the location of the watermain and the space needed for equipment. Where possible, crews are completing this work during the day, with efforts to keep roads and businesses open and accessible.
There are more watermain connections ahead, and some will require temporary water shutdowns. Here’s what you need to know:
- Some connections can be completed without interrupting water service.
- If a building is without water, affected occupants will receive at least 48 hours' notice.
- Most shutdowns are expected to last between four and eight hours, depending on the location and complexity of the work.
With the new watermain connected, crews have also started individual service connections on Elm Street, west of Mountain Road.
Elm Street: More crews working on service connections
A third crew is now on site digging service trenches ahead of the reconnection crew. This additional crew is helping move the work along more quickly.
Unlike larger watermain connections, individual service connections are generally quicker, usually taking approximately 30 to 60 minutes per building. During this time, the building's water service will be temporarily shut off while the old connection is disconnected and the new one is hooked up.
Once the underground work is complete, a separate subcontractor will return for final restoration, including sidewalks, curbs and sod. Some restoration work, particularly sod, is expected to continue into 2027.
LOOK AHEAD: WHAT TO EXPECT THIS WEEK
Here’s a look at the work planned for the next few days:

Wednesday, November 18
- Crews will install the Balsam Lane hydrant and connection, along with a large-diameter service on Main Street East.
- Servicing work on Main Street East will necessitate a single lane closure.
- Some parking near the work area on Balsam will be affected, but most of the parking lot will remain open.
Thursday, November 19
- Crews will complete watermain connections to Oak Street and the GBF.
- A temporary water shutdown will affect all of Oak Street. Notices have been hand-delivered to affected properties.
Friday, November 20
- If the scheduled work is completed on time, crews will return to Main Street East to connect services between Robinson Street and Elm Street.
- One lane will be closed while the excavator works from the roadway toward the buildings. Flag persons will direct traffic through the area.
- Sidewalks will close temporarily as equipment crosses them. The contractor and flag persons will help direct pedestrians around the work zone.
Mountain Road: Updated reopening plan
Last week, we anticipated that the road would reopen by mid-week. However, water testing progressed faster than expected, allowing the project team to adjust the sequence of work.
If water samples pass, crews plan to complete the watermain connection at Mountain Road, along with the service connections between Elm Street and Main Street, next week.
Rather than reopen Mountain Road now and close it again to complete this work, the plan is to finish this section before reopening the road. This will avoid the need for further daytime closures in this area for that work.
The current target is to reopen Mountain Road by the end of the day on Friday, November 27.
Please note that some overnight full road closures will still be required for watermain connections at Christie Street and Main Street, as well as at Elm Street and Mountain Road.
We recognize that construction can bring temporary disruptions to daily routines and appreciate your patience and understanding as crews complete this important infrastructure work.
THANK YOU FOR YOUR PATIENCE
We recognize that construction brings temporary changes to daily routines. Our goal is to provide clear, timely information to help make construction as predictable and manageable as possible.
Thank you for your continued patience and support as we work together to reimagine downtown Grimsby.
STAY CONNECTED
Project News and Updates
Never miss an update! Visit www.letstalkgrimsby.ca/dr-construction and select "Follow Project" to receive construction updates directly in your inbox.
Follow Downtown Reimagined
Stay connected through our official Facebook and Instagram channels:
Questions?
Email DTreimagined@grimsby.ca

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends