Peach King Centre Expansion and Renovation Project
Share Peach King Centre Expansion and Renovation Project on FacebookShare Peach King Centre Expansion and Renovation Project on TwitterShare Peach King Centre Expansion and Renovation Project on LinkedinEmail Peach King Centre Expansion and Renovation Project link
Big things are coming to Grimsby!
Background
In 2019, a citizen-driven Parks, Recreation and Culture Master Plan identified the need to improve opportunities for community recreation and access to indoor facility space in Grimsby. To achieve this, one of the top recommendations was to work towards a multi-use recreation facility on the Peach King Centre Grounds.
In late August 2019, federal and provincial funding opportunities were announced and Council approved an expedited preparation of a concept plan for a Peach King Centre Expansion. In 2021, the project was selected for approval through the Ontario Government's Strategic Priorities Infrastructure Fund (SPIF), with the province contributing a grant of $16 million towards the total project cost.
Moving from the original concept in 2019 to 2023, there has been an unprecedented increase in both the cost of construction and the overall local demand for recreation space. In response to these two pressures, Council has approved an updated project budget of $36.7 Million that includes expanded project components such as a double gymnasium, fitness studio, expanded lobbies, and select green building initiatives. The comprehensive list of project components is detailed below.
Project Components
The proposed project includes a mix of renovation and expansion items for the existing Peach King Centre. The two ice pads at the Peach King Centre will remain with the following items planned for the project.
A double gymnasium (dividable)
A second-floor indoor walking track (above gymnasium)
Multi-use community rooms
Fitness centre
Fitness studio
Youth Centre
Reflection Room
Concession
West Pad Dressing Room improvements
Parking improvements
Design Status
The project has completed design development and is working through the contract documents stage. Please see the design plans and rendering section for project floor plans and renderings.
Construction
Aquicon Construction was retained in September 2023 to act as the project's construction manager. Construction windows are estimated as follows:
May 1 2024 - The Peach King Centre (PKC) closes to the public to prepare for construction.
May 1 - 12 2024 - The building is opened as needed to accommodate ice bookings only (evenings and weekends).
Fitness Centre and Raquetball courts are fully closed.
Customer Service Desk relocates to the Livingston Activity Centre.
May 13 2024 - PKC is fully closed and construction commences.
September 2024 - PKC opens for ice-only operations while construction continues.
April 1 2025 - Ice is removed and PKC is fully closed to the public. Construction continues.
Early Fall 2025 - Construction is complete and the facility reopens.
Get Involved
As the project moves forward, there will be opportunities for residents and community groups to provide feedback. Stay Informed by clicking the "Subscribe" button on this page and following the Town of Grimsby on Facebook, Instagram and Twitter.
Big things are coming to Grimsby!
Background
In 2019, a citizen-driven Parks, Recreation and Culture Master Plan identified the need to improve opportunities for community recreation and access to indoor facility space in Grimsby. To achieve this, one of the top recommendations was to work towards a multi-use recreation facility on the Peach King Centre Grounds.
In late August 2019, federal and provincial funding opportunities were announced and Council approved an expedited preparation of a concept plan for a Peach King Centre Expansion. In 2021, the project was selected for approval through the Ontario Government's Strategic Priorities Infrastructure Fund (SPIF), with the province contributing a grant of $16 million towards the total project cost.
Moving from the original concept in 2019 to 2023, there has been an unprecedented increase in both the cost of construction and the overall local demand for recreation space. In response to these two pressures, Council has approved an updated project budget of $36.7 Million that includes expanded project components such as a double gymnasium, fitness studio, expanded lobbies, and select green building initiatives. The comprehensive list of project components is detailed below.
Project Components
The proposed project includes a mix of renovation and expansion items for the existing Peach King Centre. The two ice pads at the Peach King Centre will remain with the following items planned for the project.
A double gymnasium (dividable)
A second-floor indoor walking track (above gymnasium)
Multi-use community rooms
Fitness centre
Fitness studio
Youth Centre
Reflection Room
Concession
West Pad Dressing Room improvements
Parking improvements
Design Status
The project has completed design development and is working through the contract documents stage. Please see the design plans and rendering section for project floor plans and renderings.
Construction
Aquicon Construction was retained in September 2023 to act as the project's construction manager. Construction windows are estimated as follows:
May 1 2024 - The Peach King Centre (PKC) closes to the public to prepare for construction.
May 1 - 12 2024 - The building is opened as needed to accommodate ice bookings only (evenings and weekends).
Fitness Centre and Raquetball courts are fully closed.
Customer Service Desk relocates to the Livingston Activity Centre.
May 13 2024 - PKC is fully closed and construction commences.
September 2024 - PKC opens for ice-only operations while construction continues.
April 1 2025 - Ice is removed and PKC is fully closed to the public. Construction continues.
Early Fall 2025 - Construction is complete and the facility reopens.
Get Involved
As the project moves forward, there will be opportunities for residents and community groups to provide feedback. Stay Informed by clicking the "Subscribe" button on this page and following the Town of Grimsby on Facebook, Instagram and Twitter.
Share PKC Expansion and Renovation Survey on FacebookShare PKC Expansion and Renovation Survey on TwitterShare PKC Expansion and Renovation Survey on LinkedinEmail PKC Expansion and Renovation Survey link
July 8 2021 - Provincial Announcement for the Project Funding
Peach King Centre Expansion and Renovation Project has finished this stage
MPP Sam Oosterhoff delivers the great news that the Peach King Centre Expansion Project is receiving a $16 million dollar investment from the Province of Ontario.
April 2022 - SPIF Agreement is finalized
Peach King Centre Expansion and Renovation Project has finished this stage
With the SPIF Agreement finalized this project is ready to push ahead!
Project Management Firm Selection
Peach King Centre Expansion and Renovation Project has finished this stage
Colliers Project Leaders joined the project in July 2022.
Design Team Selection
Peach King Centre Expansion and Renovation Project has finished this stage
McCallumSather Architects are selected as the project's design consultant.
Schematic Design Approval
Peach King Centre Expansion and Renovation Project has finished this stage
Town Council Approves the Schematic Design of the Peach King Centre Expansion and Renovation
Construction Manager Selection
Peach King Centre Expansion and Renovation Project has finished this stage
This is expected to be completed in September 2023
Public Open House - September 27
Peach King Centre Expansion and Renovation Project has finished this stage
Join us on September 27th @ 6:30pm in the PKC Auditorium for a public open house to learn more about the project and give your feedback.
Design Development Completion
Peach King Centre Expansion and Renovation Project has finished this stage
February 2024 - The project complete the Design Development milestone.
Groundbreaking
Peach King Centre Expansion and Renovation Project has finished this stage
On May 21 2024, Mayor Jeff Jordan and Town Council were joined by Amarjot Sandhu, Parliamentary Assistant to Ontario’s Minister of Infrastructure, and Sam Oosterhoff, MPP for Niagara West, to celebrate the groundbreaking of the Peach King Centre (PKC) Expansion and Renovation.
Construction Commences
Peach King Centre Expansion and Renovation Project is currently at this stage
Construction has now started. Demolition is scheduled for June 2024 and footings and structure will begin in the early summer.
PKC Reopens for Temporary Operations
this is an upcoming stage for Peach King Centre Expansion and Renovation Project
The facility will reopen from September 2024 to March 2025 during construction for ice operations only.
Project Completion - Fall 2025
this is an upcoming stage for Peach King Centre Expansion and Renovation Project
The Expanded and Renovated Peach King Centre is expected to fully reopen in late Fall 2025.